Vietnam bridge, road and highway development projects

Vietnam is pushing ahead with a series of road, highway and bridge projects that will improve the country’s transport network. Feasibility studies for three stretches of the North-South Expressway have been received by Vietnam’s Ministry of Transport (MoT). The 29km stretch from Nha Trang to Cam Lam is expected to cost US$177.9 million, with work starting in 2019 and due for completion in 2021. The 60km stretch from Dau Giay to Tan Phu will be built from 2018 to 2022. The 101km stretch from Vinh Hao to Pha
June 20, 2018 Read time: 2 mins
Vietnam is pushing ahead with a series of road, highway and bridge projects that will improve the country’s transport network.


Feasibility studies for three stretches of the North-South Expressway have been received by Vietnam’s Ministry of Transport (MoT). The 29km stretch from Nha Trang to Cam Lam is expected to cost US$177.9 million, with work starting in 2019 and due for completion in 2021. The 60km stretch from Dau Giay to Tan Phu will be built from 2018 to 2022. The 101km stretch from Vinh Hao to Phan Thiet is being constructed through the build-operate-transfer (BOT) model. The 64km stretch from Ninh Binh to Thanh Hoa will take three years to build and is expected to cost $613 million.

Work is commencing on the $342 million Hoang Cau-Voi Phuc Road project in Hanoi. The project to build the 2.2km stretch includes two overpasses crossing the Nguyen Chi Thanh and Hoang Cau-Voi Phuc crossroads and the Giang Vo-Lang Ha and Hoang Cau-Voi Phuc crossroads.

Designs are currently being assessed for the proposed Can Gio Bridge project by the People's Committee of Ho Chi Minh City (HCMC). The bridge is intended to replace the Binh Kanh ferry link, improving connections to central Hanoi. The new bridge will span Cha River and Soai Rap River, running between Can Gio and Nha Be District and measuring 7.4km in length.

Loans worth nearly $301 million will pay for work on the Trung Luong-My Thuan Expressway project. The four banks are the Bank for Investment and Development of Vietnam (BIDV), the Vietnam Bank for Industry and Trade (VietinBank), the Vietnam Bank for Agriculture and Rural Development (Agribank) and the Vietnam Prosperity Commercial Bank (VPBank). The route is being built by contractor BOT Trung Luong-My Thuan JSC.

Other projects include highways linking La Son District with Cam Lo District, Ba Bot District with Cao Bo District as well as Nha Trang City with My Thuan 2 Bridge and Dau Giay Town.

Related Content

  • Vietnam expressway deal moving forward
    January 16, 2019
    A pre-feasibility study is being planned for Vietnam’s Hoa Binh-Moc Chau Expressway project. Construction of the expressway is expected to cost US$857.4 million, with the work being handled under the PPP model. The 85km is planned to feature two lanes in either direction. Construction of the expressway is expected to reduce journey times between Hanoi and Son La, close to the border with Laos, from six hours at present, to just 2.5 hours in the future.
  • Vietnam’s latest highway and tunnel projects
    October 21, 2014
    In Vietnam work is now being carried out on a new highway to connect southern province to Central Highlands, while progress is being achieved on the Ca Pass Tunnel project. A 200km highway has been proposed that will link Dong Nai province with Lam Dong province. The project would extend from Thong Nhat Commune in Dong Nai to Lam Dong's Lien Khuong-Prenn highway and is subject to approval from Vietnam’s Ministry of Transport. The project will commence in 2015 if the required approval is given, and will then
  • Vietnam expressway deal agreed
    November 1, 2019
    An agreement has been reached in Vietnam over an important expressway project to improve transport to and from Ho Chi Minh City.
  • Vietnam plans bridge link upgrade
    July 10, 2017
    A bridge project is being planned in Vietnam’s Ho Chi Minh City that will span the Saigon River. The project is for the Thu Thiem 4 Bridge, which will measure 2.16km and connect District 2 with District 7.