UK: Mott MacDonald reports £56 million FARRRS highway is open

Mott MacDonald Construction reports that the £56 million Finningley and Rossington Regeneration Route Scheme - FARRRS - in Doncaster, UK, has been completed and open. Mott MacDonald provided Doncaster Council with the majority of pre-construction services on the project. Planning for a link connecting the south of Doncaster to Junction 3 of the M18 started over a decade ago. The first phase, known as Great Yorkshire Way, comprises 1.5km of new dual carriageway and 3km of single carriageway. It also includes
March 21, 2016 Read time: 2 mins
2579 Mott MacDonald Construction reports that the £56 million Finningley and Rossington Regeneration Route Scheme - FARRRS - in Doncaster, UK, has been completed and open.

Mott MacDonald provided Doncaster Council with the majority of pre-construction services on the project.

Planning for a link connecting the south of Doncaster to Junction 3 of the M18 started over a decade ago. The first phase, known as Great Yorkshire Way, comprises 1.5km of new dual carriageway and 3km of single carriageway. It also includes two new rail as four new bridges over local watercourses.

The consultancy also provided project management support throughout and offered technical support during construction. Prior to construction Mott MacDonald carried out environmental and traffic appraisals, provided assistance at public consultations, prepared the planning application, drafted the compulsory purchase and side road orders and undertook the majority of design work.

Mott MacDonald is now providing similar services to the council for the second phase of FARRRS, which will complete the road from the A638 to Doncaster Sheffield Airport.

For more information on companies in this article

Related Content

  • Construction of Fehmarn Belt Link could start in 2019
    February 27, 2018
    Construction of a Fehmarn Belt Link could start a year from now – more than a year ahead of schedule, according to Danish media reports. The timing was put forward by Holger Schou Rasmussen, chairman of Femernbælt Development, and Kristian Pihl Lorenzen, the Liberal Party spokesman for traffic issues. They reportedly said that a pending environmental court case in Germany that has stalled approval by German authorities won’t hold up construction of the 18km crossing as much as had been feared. As late as
  • New structure for A46 bypass
    January 10, 2025
    A new concrete structure is being built for the UK’s A46 bypass.
  • Kapsch TrafficCom’s the Tolling Wizard of Oz
    April 4, 2014
    Standfirst: Leading tolling technology solution manufacturer Kapsch TrafficCom has recently been appointed to deliver two major electronic tolling projects in Australia, as Guy Woodford reports Kapsch TrafficCom’s new key Australian contracts will see the Austrian firm use its multi-lane free-flow (MLFF) single gantry solution on the Eastern Distributor toll road in Sydney and the Legacy Way toll road in Brisbane. The MLFF single gantry solution includes innovative stereoscopic vehicle detection and classi
  • Cleveland Bridge on A1 project in the UK
    February 7, 2017
    Cleveland Bridge UK has delivered a significant upgrade project on the A1 in North Yorkshire, England, with the fabrication and installation of eight bridges. Using British-made steel, the 20-month project was completed with the installation of the 53m Fort Overbridge. The work was carried out on behalf of Highways England’s principal contractor on the A1 scheme, a Carillion and Morgan Sindall joint venture. The A1 Leeming to Barton upgrade is replacing the dual carriageway with a three-lane motorw