Thailand rekindles interest in the motorway in Bang Pa-in

The Thai government expects to announce contractors for construction of two motorway sections this month after steel price hikes derailed a recent tender process. The sections are part of the 196km motorway connecting Bang Pa-in district in Ayutthaya with Nakhon Ratchasima in the northeast, according to a report in the Bangkok Post. The project, costing nearly US$2 billion, is divided into 40 sections, 25 of which are scheduled to be built this year. But the Highways Department has signed only one con
July 6, 2016 Read time: 2 mins
The Thai government expects to announce contractors for construction of two motorway sections this month after steel price hikes derailed a recent tender process.

The sections are part of the 196km motorway connecting Bang Pa-in district in Ayutthaya with Nakhon Ratchasima in the northeast, according to a report in the Bangkok Post.

The project, costing nearly US$2 billion, is divided into 40 sections, 25 of which are scheduled to be built this year. But the Highways Department has signed only one contractor so far, for construction of a 3.6km section in Saraburi, the Post reported. The department had to cancel the bidding on five sections because the winners -- Italian-Thai Development and Nawarat Patanakarn – raised their prices after a 40% rise in steel prices.

The Post quoted unnamed sources in the Highways Department saying discussions failed between the government and two winners to reach a new price, meaning another bidding round will be scheduled. The department is also now revising its own cost estimates for the highway construction.

Related Content

  • Investing in East Africa's road sector to boost economic development
    April 14, 2020
    Investments in East Africa’s road sector are helping drive economic development as well as political stability
  • Bertha restarts work on Seattle’s Alaskan Highway Viaduct project
    September 19, 2016
    Bertha, the tunnelling machine that is making its way under the US city of Seattle, has restarted work after nearly three weeks of scheduled maintenance downtime. The machine has been sitting more than 51m underground while crews replaced of 14 large cutting tools, according to the Washington State Department of transportation. Each tool weighs just under 275kg. Bertha - as the SR 99 tunnelling machine is called – is working on the Alaskan Way Viaduct Replacement Program. The Alaskan Way is an elevate
  • Thailand’s key highway plans
    January 8, 2021
    Progress is being achieved for Thailand’s key highway projects.
  • Fehmarn Belt Fixed Link could open by 2025 at earliest
    November 27, 2015
    The ambitious Fehmarn Belt Fixed Link, connecting Denmark and Germany, will open in 2025 at the earliest, according to the Danish finance ministry. Femern A/S, the Danish government-owned company managing the project, confirmed the note from the government. It also said the ministry still has financial concerns over the deal to build an immersed tunnel connecting the towns of Rødby in Denmark’s southern Zealand with Puttgarden in northern Germany. Of particular is the time for a construction company t