Taiwan bureau threatens Kuo Teng over its Kinmen Bridge work

Taiwan’s National Expressway Engineering Bureau said it would terminate its contract with Kuo Teng Construction company because of issues over the construction schedule of Kinmen Bridge. Work on the bridge connecting the main island of Greater Kinmen and Lieyu, also known as Little Kinmen, began in 2013 after it had been a campaign promise in five presidential elections. The bureau recently said that work on the bridge was nearly 19% behind schedule and reportedly gave the company 30 days to bring the pro
June 2, 2016 Read time: 2 mins
Taiwan’s National Expressway Engineering Bureau said it would terminate its contract with Kuo Teng Construction company because of issues over the construction schedule of Kinmen Bridge.

Work on the bridge connecting the main island of Greater Kinmen and Lieyu, also known as Little Kinmen, began in 2013 after it had been a campaign promise in five presidential elections.

The bureau recently said that work on the bridge was nearly 19% behind schedule and reportedly gave the company 30 days to bring the project back on schedule.

The Taipei Times reported that it could lead to a change of contractor for a third time.

Kuo Teng Construction has also been told to increase the number of workers, speed up material delivery to the site and to use more efficient equipment.

“The contractor failed to bring in partners that were equipped with better machinery for the project, even though it was facing a shortage of workers and construction materials and clearly lacks the ability to handle the project on its own,” the bureau said in a statement. “The contractor had fallen behind the construction schedule by 16%...which shows that it has neither the ambition nor the determination to expedite the progress of the work.”

The Times also reported that the bureau had informed Kuo Teng Construction in February that delays to the bridge’s construction meant the firm was barred from bidding for government projects for one year.

Public construction commission minister Wu Hong-mo was reported saying most government agencies prefer to choose the bidders that offer the cheapest packages, fearing criticism that otherwise they would be wasting taxpayers’ money.

Wu said his top priority is to make sure government workers are not afraid to hire firms that present the most comprehensive bids, adding that the commission would lay out the types of projects to which this bidding method applies.

Related Content

  • Bridge engineering worldwide
    July 1, 2013
    Guy Woodford looks at vital bridge construction, repair and inspection projects in China, Europe, North America and Australia The Heron Road Bridge in Ottawa, Ontario in Canada is a vital link within the City’s transport network, as it crosses the Rideau River, which divides the east and west parts of the City. Constructed in 1966-1967, the Heron Road Bridge is approximately 275m long and includes six lanes.
  • Bridge inspection: destructive versus non-destructive methods
    January 6, 2015
    Tens of thousands of bridges in the United States are in desperate need of repair. But where to begin analysing their deteriorating state? Roger Roberts* investigates tips and techniques for ensuring bridge safety The average age of America’s more than 600,000 crumbling bridges is 42 years – many are 60 to 80 years old. The situation is dire, with many described as functionally obsolete, according to the American Society of Civil Engineers’ latest edition of its Report Card for America’s Infrastructure.
  • Indonesia plans $490 billion infrastructure spend over the next five years
    October 8, 2014
    According to the government of Indonesia, US$490.7 billion (IDR 6,000 trillion) will be needed in the next five years for a series of major infrastructure projects across the country including roads, bridges, power plants, ports and airports. The government hopes that investment projects like these will boost its economic growth rate to 7% per annum versus 5% this year. This latest announcement follows on from an Indonesian government report last November, which unveiled plans to invest $35 billion in new
  • Slovakia’s R2 Expressway moves a step closer
    June 4, 2018
    Slovakia said it will tender this year for the 14km R2 expressway linking Roznava and Jablonov nad Turnov with completion likely in 2024. Slovakia's transport minister Arpad Ersek said construction could start by Q3 2019. R2 is a 360km route that will run from Kosice in the east across the country to Trenčín, near the Czech border in the west. It will pass through Bánovce nad Bebravou, Prievidza and Lučenec. Roznava is an economic and tourist centre around 70km from Kosice.