Taiwan bridge link project moving ahead

Construction of the Kinmen Bridge in Taiwan has now been resumed, with work having restarted on the project in late 2016. The bridge will be 5.4km long in all and will have a 1.05km long main section, connecting the islands of Greater Kinmen and Little Kinmen (also known as Lieyu). The project includes building approach roads for the bridge as well as cuttings and connecting ramps. Costing US$292 million and with funding being provided jointly by Taiwan’s Government and the local authorities, the bridge is
February 23, 2017 Read time: 2 mins
Construction of the Kinmen Bridge in Taiwan has now been resumed, with work having restarted on the project in late 2016. The bridge will be 5.4km long in all and will have a 1.05km long main section, connecting the islands of Greater Kinmen and Little Kinmen (also known as Lieyu). The project includes building approach roads for the bridge as well as cuttings and connecting ramps. Costing US$292 million and with funding being provided jointly by Taiwan’s Government and the local authorities, the bridge is of enormous importance to Taiwan.

Taiwan’s Ministry of Public Construction Commission has called for the project to be prioritised and ready for use by the end of 2019. This will bring the completion date ahead of the planned September 2020 opening announced by the Taiwan Area National Expressway Engineering Bureau when work restarted.

However the Kinmen Bridge project has a troubled past. It was approved by the Council for Economic Planning and Development in early 2010 and construction work then commenced in the second quarter of 2013, but was beset by delays and problems with contractors.

By mid-2016, construction was behind schedule, with accusations that the contractor was unable to provide the machines, materials or expertise required to carry out the work. When the firm building the bridge, Kuo Teng Construction, then proved unable (or unwilling) to bring in sufficient help from other companies to get the work back on track, it had its contract terminated as a result. The Taiwan Area National Expressway Engineering Bureau then put the contract out to tender once more.

Related Content

  • Norway's bridge meets tough environmental targets
    February 27, 2012
    One of the world's longest bridges is being built in Norway – for traffic volumes of just 2,000 cars/day reports Adrian Greeman. The stunning landscape of the long sea fjords in Norway is one of its glories, attracting thousands of tourists every summer. But the high mountains and deep sea inlets are also one of the great obstacles to transport and development.
  • Colombia’s troubled tunnel project completion due
    April 26, 2017
    The completion of work on Colombia’s troubled tunnel project is now finally in sight. A new contractor will be selected by Colombia's National Road Institute (Invias) to complete the last section of work required on the La Linea Tunnel. The winner of the tender process will be announced on 13th June 2017. An additional US$50 million is being budgeted by the Colombian authorities to complete the work. It is expected that in all, finishing the project will cost $86.6 million. Work still to be carried out incl
  • Sunderland’s New Wear Crossing takes shape
    February 16, 2017
    The New Wear Crossing will be the first bridge to be built over the River Wear in Sunderland, UK, for more than 40 years Raising the bridge’s 100m-tall pylon promised to be a stunning visual sight, but also a tricky operation dictated by extremely variable local weather. World Highways went to press just before the operation, but not before the pylon had arrived by barge on January 7. It had completed a two-day crossing of the often unpredictable North Sea from the Belgian port of Ghent where it was f
  • New road links will cut congestion in St Petersburg
    June 20, 2016
    Road building will solve the problem of traffic jams in St Petersburg – Eugene Gerden writes The authorities in Russian city St Petersburg plan to solve the problem of traffic jams in the city during the next few years. The strategy is expected to be achieved through road building and the improvement of transport connections between different districts in the city. Implementation of these plans will take place as part of the decree 355 "Of the Strategy of St Petersburg Economic and Social Development