Strabag closes in on Poland’s S8 Marki-Kobylka contract

Strabag has nudged into the lead for Poland’s retender of the dual lane S8 section between the Marki and Kobylka junctions, previously held by Salini-Impreglio. Five offers were on the table for the deal with Strabag offering €38 million, well above the €32 million that was budgeted for by GDDKiA, Poland’s road authority. Other bids came from a consortium headed by Warszawskie Przedsiebiorstwo Mostowe Mosty at nearly €40 million, a PORR and Unibep consortium offere at almost €59 million, a bid by I
August 19, 2019 Read time: 2 mins
945 Strabag has nudged into the lead for Poland’s retender of the dual lane S8 section between the Marki and Kobylka junctions, previously held by Salini-Impreglio.  


Five offers were on the table for the deal with Strabag offering €38 million, well above the €32 million that was budgeted for by 1361 GDDKiA, Poland’s road authority.

Other bids came from a consortium headed by Warszawskie Przedsiebiorstwo Mostowe Mosty at nearly €40 million, a PORR and Unibep consortium offere at almost €59 million, a bid by Intercor at nearly €65 million and one by and Budimex at just over €39 million.

GDDKiA expects to sign a contract in November with completion set for spring 2021.
 
The contract is one two that make up construction of a 15km section of the S8 expressway. The consortium from Salini was responsible for the implementation of the first contract. The second has already been completed.

More than 500km of the planned 565km S8 road have been built since construction started in 2003. It runs from Wrocław to Białystok via Łódź and the capital Warsaw.

Originally, the road was to continue to the border with Lithuania, but in 2009 the plans were changed and currently the S61 will branch off the S8 and go to the border.

The S8 section from Warsaw to the S61 interchange is planned to become part of the Via Baltica, a stretch of the European route E 67.

Via Baltica runs from the Czech Republic to Helsinki in Finland by way of Poland, Lithuania, Latvia and Estonia. It goes via Prague, Wrocław, Warsaw, Kaunas, Panevėžys, Riga, Tallinn and Helsinki. The final stretch between the Estonian capital Tallinn and the Finnish capital Helsinki is by ferry, a two-and-a-half hour crossing of the Gulf of Finland.

For more information on companies in this article

Related Content

  • New road now open to traffic in Rwanda
    September 24, 2015
    A major road project in Rwanda has been completed on schedule by contractor STRABAG. The rebuilt road’s route runs 78km and connects capital Kigali with the border town of Gatuna. STRABAG won the contract to reconstruct the road in July 2011. The construction phase commences in January 2012 and took 44 months to complete. The official opening took place in the presence of Rwanda’s Minister of Infrastructure James Musoni and Neven Mimica, the European Union Commissioner for International Cooperation and Deve
  • Somague consortium wins deal for Ponte 25 de Abril
    September 27, 2018
    Portuguese infrastructure operator Infraestruturas de Portugal has awarded Somague a €12.6 million maintenance and refurbishment contract for work on the bridge Ponte 25 de Abril. Somague is heading up a consortium that includes Sociedade de Montagens Metalomecânicas and Reparação, Consolidação e Modificação de Estruturas. The 25 de Abril, a 2.3km suspension bridge for vehicles and trains over the Tagus River, connects Portugal’s capital city Lisbon to the municipality of Almada. It was built by the A
  • Strabag in Hungary M6 deal
    November 10, 2020
    The southernmost Bóly-Ivándárda section is the last M6 section to be built.
  • STRABAG wins contract for Hamburg, Germany
    August 26, 2020
    STRABAG has won a major highway contract in Hamburg, Germany.