Strabag closes in on Poland’s S8 Marki-Kobylka contract

Strabag has nudged into the lead for Poland’s retender of the dual lane S8 section between the Marki and Kobylka junctions, previously held by Salini-Impreglio. Five offers were on the table for the deal with Strabag offering €38 million, well above the €32 million that was budgeted for by GDDKiA, Poland’s road authority. Other bids came from a consortium headed by Warszawskie Przedsiebiorstwo Mostowe Mosty at nearly €40 million, a PORR and Unibep consortium offere at almost €59 million, a bid by I
August 19, 2019 Read time: 2 mins
945 Strabag has nudged into the lead for Poland’s retender of the dual lane S8 section between the Marki and Kobylka junctions, previously held by Salini-Impreglio.  


Five offers were on the table for the deal with Strabag offering €38 million, well above the €32 million that was budgeted for by 1361 GDDKiA, Poland’s road authority.

Other bids came from a consortium headed by Warszawskie Przedsiebiorstwo Mostowe Mosty at nearly €40 million, a PORR and Unibep consortium offere at almost €59 million, a bid by Intercor at nearly €65 million and one by and Budimex at just over €39 million.

GDDKiA expects to sign a contract in November with completion set for spring 2021.
 
The contract is one two that make up construction of a 15km section of the S8 expressway. The consortium from Salini was responsible for the implementation of the first contract. The second has already been completed.

More than 500km of the planned 565km S8 road have been built since construction started in 2003. It runs from Wrocław to Białystok via Łódź and the capital Warsaw.

Originally, the road was to continue to the border with Lithuania, but in 2009 the plans were changed and currently the S61 will branch off the S8 and go to the border.

The S8 section from Warsaw to the S61 interchange is planned to become part of the Via Baltica, a stretch of the European route E 67.

Via Baltica runs from the Czech Republic to Helsinki in Finland by way of Poland, Lithuania, Latvia and Estonia. It goes via Prague, Wrocław, Warsaw, Kaunas, Panevėžys, Riga, Tallinn and Helsinki. The final stretch between the Estonian capital Tallinn and the Finnish capital Helsinki is by ferry, a two-and-a-half hour crossing of the Gulf of Finland.

For more information on companies in this article

Related Content

  • D8 highway in Czech Republic delayed
    September 19, 2013
    Completion of the final stretch of the D8 highway in the Czech Republic will be delayed. The 4.7km section of highway in the Czech region of Usti Nad Labem Oldrich Bubenicek will not be built by 2015 as planned originally. A landslide that occurred near Litochovice in June 2013 is the reason for the delay. Additional geotechnical surveys now have to be carried out before work can commence to to repair the damage cause by the landslide. It is possible that the results of the survey work will show that the ro
  • Green light for S6 dual carriageway section in Zachodniopomorskie
    December 14, 2016
    Poland’s Zachodniopomorskie province has given the go-ahead to the consortium set up by Dragados and Polaqua to start construction of a section of the S6. A deal was done in October 2015 for work on the 24km section of the dual carriageway between Kielpino and Kolobrzeg. The cost is estimated to be nearly €105 million. Meanwhile, a section of the S19 express road - between Slawinek junction and the northern part of the Lublin city ring road – was opened this month. Budimex built the 10km stretch in so
  • Legal tangle over Polish highway project
    February 29, 2012
    The complex legal tangle over Poland's troubled A2 highway project is continuing to develop.
  • Czech republic to complete 80km of motorway out of 230km
    July 3, 2017
    The Czech government said that around 80km of highways out of 230km under construction will be finished this year. Completed work includes the upgraded sections of the D1 motorway.