Strabag closes in on Poland’s S8 Marki-Kobylka contract

Strabag has nudged into the lead for Poland’s retender of the dual lane S8 section between the Marki and Kobylka junctions, previously held by Salini-Impreglio. Five offers were on the table for the deal with Strabag offering €38 million, well above the €32 million that was budgeted for by GDDKiA, Poland’s road authority. Other bids came from a consortium headed by Warszawskie Przedsiebiorstwo Mostowe Mosty at nearly €40 million, a PORR and Unibep consortium offere at almost €59 million, a bid by I
August 19, 2019 Read time: 2 mins
945 Strabag has nudged into the lead for Poland’s retender of the dual lane S8 section between the Marki and Kobylka junctions, previously held by Salini-Impreglio.  


Five offers were on the table for the deal with Strabag offering €38 million, well above the €32 million that was budgeted for by 1361 GDDKiA, Poland’s road authority.

Other bids came from a consortium headed by Warszawskie Przedsiebiorstwo Mostowe Mosty at nearly €40 million, a PORR and Unibep consortium offere at almost €59 million, a bid by Intercor at nearly €65 million and one by and Budimex at just over €39 million.

GDDKiA expects to sign a contract in November with completion set for spring 2021.
 
The contract is one two that make up construction of a 15km section of the S8 expressway. The consortium from Salini was responsible for the implementation of the first contract. The second has already been completed.

More than 500km of the planned 565km S8 road have been built since construction started in 2003. It runs from Wrocław to Białystok via Łódź and the capital Warsaw.

Originally, the road was to continue to the border with Lithuania, but in 2009 the plans were changed and currently the S61 will branch off the S8 and go to the border.

The S8 section from Warsaw to the S61 interchange is planned to become part of the Via Baltica, a stretch of the European route E 67.

Via Baltica runs from the Czech Republic to Helsinki in Finland by way of Poland, Lithuania, Latvia and Estonia. It goes via Prague, Wrocław, Warsaw, Kaunas, Panevėžys, Riga, Tallinn and Helsinki. The final stretch between the Estonian capital Tallinn and the Finnish capital Helsinki is by ferry, a two-and-a-half hour crossing of the Gulf of Finland.

For more information on companies in this article

Related Content

  • Poland's complex road dispute
    March 1, 2012
    The complex legal case between the Polish General Directorate for National Roads and Motorways (GDDKiA) and Austrian contractor Alpine Bau is continuing in the Polish courts.
  • Polish projects planned to open
    January 17, 2018
    Nearly 450km of new roads will be added to the Polish road network during 2018. Of these close to 410km will be of dual carriageways. According to the Polish roads authority GDDKiA, the figure of 450km will beat the record 350km of roads constructed in 2018. This will also beat the earlier record of 330km of dual carriageways, which was set in 2012. Some of the road completions involve long stretches such as the entirety of the Dual carriageways that will be completed include the S8 between Warsaw and
  • Prep starts on Lithuania’s A14 reconstruction
    November 4, 2021
    A short section of the Vilnius-Utena A14 - Lithuania's only concrete surface highway - was completed a few years ago.
  • Finnish Motorway Finally finished: Finland's M1
    July 23, 2012
    It has taken a long time to complete, but a vital motorway link is open to traffic as Heikki Harri reports After almost 50 years of construction, the M1 motorway linking Helsinki, the Finnish capital city and Turku, the country's old capital in the southwest, is finally completed. It did not take all 50 years of construction but the first section from Helsinki towards the west was constructed in the mid -1960s. Then there was a pause until mid-1990s when the works resumed section by section. The final sect