Strabag closes in on Poland’s S8 Marki-Kobylka contract

Strabag has nudged into the lead for Poland’s retender of the dual lane S8 section between the Marki and Kobylka junctions, previously held by Salini-Impreglio. Five offers were on the table for the deal with Strabag offering €38 million, well above the €32 million that was budgeted for by GDDKiA, Poland’s road authority. Other bids came from a consortium headed by Warszawskie Przedsiebiorstwo Mostowe Mosty at nearly €40 million, a PORR and Unibep consortium offere at almost €59 million, a bid by I
August 19, 2019 Read time: 2 mins
945 Strabag has nudged into the lead for Poland’s retender of the dual lane S8 section between the Marki and Kobylka junctions, previously held by Salini-Impreglio.  


Five offers were on the table for the deal with Strabag offering €38 million, well above the €32 million that was budgeted for by 1361 GDDKiA, Poland’s road authority.

Other bids came from a consortium headed by Warszawskie Przedsiebiorstwo Mostowe Mosty at nearly €40 million, a PORR and Unibep consortium offere at almost €59 million, a bid by Intercor at nearly €65 million and one by and Budimex at just over €39 million.

GDDKiA expects to sign a contract in November with completion set for spring 2021.
 
The contract is one two that make up construction of a 15km section of the S8 expressway. The consortium from Salini was responsible for the implementation of the first contract. The second has already been completed.

More than 500km of the planned 565km S8 road have been built since construction started in 2003. It runs from Wrocław to Białystok via Łódź and the capital Warsaw.

Originally, the road was to continue to the border with Lithuania, but in 2009 the plans were changed and currently the S61 will branch off the S8 and go to the border.

The S8 section from Warsaw to the S61 interchange is planned to become part of the Via Baltica, a stretch of the European route E 67.

Via Baltica runs from the Czech Republic to Helsinki in Finland by way of Poland, Lithuania, Latvia and Estonia. It goes via Prague, Wrocław, Warsaw, Kaunas, Panevėžys, Riga, Tallinn and Helsinki. The final stretch between the Estonian capital Tallinn and the Finnish capital Helsinki is by ferry, a two-and-a-half hour crossing of the Gulf of Finland.

For more information on companies in this article

Related Content

  • Estonia plans safety improvements for key road links
    November 1, 2019
    Estonia is planning a series of road widening and safety improvements on some key routes. The work is worth over €49 million. The roads connecting capital Tallinn with Narva, Tartu and Pärnu will all be upgraded and widened, featuring two lanes in either direction. The E20 route from Tallinn to Narva is important to Estonia economically as the latter lies close to the border with neighbouring Russia. The E263 road from Tallinn to Tartu is an important north-south road that also connects with the E67 route c
  • Priority Poland project for Portuguese firm
    February 16, 2021
    A high priority project in Poland will be handled by a Portuguese firm.
  • Polish road authority GDDKiA will re-tender for the S14
    May 12, 2017
    The Polish ministry of infrastructure announced that it will retender for building the last 27km section of the Expressway S14 around Lodz. Poland’s road authority GDDKiA said it was not satisfied with the offers it had received during the tender. They were higher than the budget by around €59 million, reaching upwards of €487 million. Local governments reportedly fear that construction delays could disrupt the Specialised Expo from June to September, 2022 if the city of Lodz were to be chosen. The wining c
  • Eurovia secures a deal for Czech D35 work
    May 30, 2018
    The Czech division of Eurovia has won a €126 million contract for a section of the D35 motorway. The Czech road and motorway management company RSD sealed the deal Eurovia, part of the Vinci Group, for construction of 14.7km between Casy and Ostrov, in the Pardubice region. Eurovia submitted a bid of nearly €126 million for the work that the government and the European Union had estimated in 2016 might cost around €194 million. Other bids had been submitted by M-Silnice and Astaldi. Eurovia recently an