Strabag closes in on Poland’s S8 Marki-Kobylka contract

Strabag has nudged into the lead for Poland’s retender of the dual lane S8 section between the Marki and Kobylka junctions, previously held by Salini-Impreglio. Five offers were on the table for the deal with Strabag offering €38 million, well above the €32 million that was budgeted for by GDDKiA, Poland’s road authority. Other bids came from a consortium headed by Warszawskie Przedsiebiorstwo Mostowe Mosty at nearly €40 million, a PORR and Unibep consortium offere at almost €59 million, a bid by I
August 19, 2019 Read time: 2 mins
945 Strabag has nudged into the lead for Poland’s retender of the dual lane S8 section between the Marki and Kobylka junctions, previously held by Salini-Impreglio.  


Five offers were on the table for the deal with Strabag offering €38 million, well above the €32 million that was budgeted for by 1361 GDDKiA, Poland’s road authority.

Other bids came from a consortium headed by Warszawskie Przedsiebiorstwo Mostowe Mosty at nearly €40 million, a PORR and Unibep consortium offere at almost €59 million, a bid by Intercor at nearly €65 million and one by and Budimex at just over €39 million.

GDDKiA expects to sign a contract in November with completion set for spring 2021.
 
The contract is one two that make up construction of a 15km section of the S8 expressway. The consortium from Salini was responsible for the implementation of the first contract. The second has already been completed.

More than 500km of the planned 565km S8 road have been built since construction started in 2003. It runs from Wrocław to Białystok via Łódź and the capital Warsaw.

Originally, the road was to continue to the border with Lithuania, but in 2009 the plans were changed and currently the S61 will branch off the S8 and go to the border.

The S8 section from Warsaw to the S61 interchange is planned to become part of the Via Baltica, a stretch of the European route E 67.

Via Baltica runs from the Czech Republic to Helsinki in Finland by way of Poland, Lithuania, Latvia and Estonia. It goes via Prague, Wrocław, Warsaw, Kaunas, Panevėžys, Riga, Tallinn and Helsinki. The final stretch between the Estonian capital Tallinn and the Finnish capital Helsinki is by ferry, a two-and-a-half hour crossing of the Gulf of Finland.

For more information on companies in this article

Related Content

  • Amomatic develops cloud-base asphalt system
    April 19, 2016
    Finnish Asphalt Plant manufacturer Amomatic has developed a cloud-based system for recording where and when asphalt loads are delivered. Two contractors – one in Finland and one in Estonia – are already using AmoTrack. “You can see where each batch was placed, what the temperature was,” said Michael Gardias, sales and business development, Africa. The information is entered via a touchscreen system which Amomatic has designed so that drivers find it easy to use.
  • Norway road project sees cost reduction
    October 25, 2017
    New technology now looks likely to reduce the cost of Norway’s massive Ferry Free E39 road project. The work had originally been expected to come with a price tag of as much as €36.47 billion (NOK 340 billion) when the plans were announced in early 2016. According to the Norwegian Public Roads Administration (Statens vegvesen), the crossing over the Bjørnafjorden is now likely to be €858.1 million (NOK 8 billion) less costly
  • Romania road works
    August 18, 2021
    Romanian road works are underway.
  • New study into the impact of weather on Europe’s transport
    November 5, 2012
    A new study into the impact of extreme weather conditions on Europe’s transport network has been carried out by Finland’s VTT Technical Research Centre. This broad-based study covered all 27 EU states and highlighted that some countries face significantly higher risks of transport disruption than others. This is the first study worldwide to evaluate risks to transport from weather phenomena on a country-specific and mode-specific basis. The study revealed that Poland faces particular problems, while other h