Strabag closes in on Poland’s S8 Marki-Kobylka contract

Strabag has nudged into the lead for Poland’s retender of the dual lane S8 section between the Marki and Kobylka junctions, previously held by Salini-Impreglio. Five offers were on the table for the deal with Strabag offering €38 million, well above the €32 million that was budgeted for by GDDKiA, Poland’s road authority. Other bids came from a consortium headed by Warszawskie Przedsiebiorstwo Mostowe Mosty at nearly €40 million, a PORR and Unibep consortium offere at almost €59 million, a bid by I
August 19, 2019 Read time: 2 mins
945 Strabag has nudged into the lead for Poland’s retender of the dual lane S8 section between the Marki and Kobylka junctions, previously held by Salini-Impreglio.  


Five offers were on the table for the deal with Strabag offering €38 million, well above the €32 million that was budgeted for by 1361 GDDKiA, Poland’s road authority.

Other bids came from a consortium headed by Warszawskie Przedsiebiorstwo Mostowe Mosty at nearly €40 million, a PORR and Unibep consortium offere at almost €59 million, a bid by Intercor at nearly €65 million and one by and Budimex at just over €39 million.

GDDKiA expects to sign a contract in November with completion set for spring 2021.
 
The contract is one two that make up construction of a 15km section of the S8 expressway. The consortium from Salini was responsible for the implementation of the first contract. The second has already been completed.

More than 500km of the planned 565km S8 road have been built since construction started in 2003. It runs from Wrocław to Białystok via Łódź and the capital Warsaw.

Originally, the road was to continue to the border with Lithuania, but in 2009 the plans were changed and currently the S61 will branch off the S8 and go to the border.

The S8 section from Warsaw to the S61 interchange is planned to become part of the Via Baltica, a stretch of the European route E 67.

Via Baltica runs from the Czech Republic to Helsinki in Finland by way of Poland, Lithuania, Latvia and Estonia. It goes via Prague, Wrocław, Warsaw, Kaunas, Panevėžys, Riga, Tallinn and Helsinki. The final stretch between the Estonian capital Tallinn and the Finnish capital Helsinki is by ferry, a two-and-a-half hour crossing of the Gulf of Finland.

For more information on companies in this article

Related Content

  • Work soon to start on Bosnia’s Hranjen Tunnel
    February 27, 2019
    Work is expected to start soon on Bosnia’s Hranjen Tunnel, part of the future Goražde-to-Sarajevo highway. Gorazde Emir Okovic, head of the Podrinje Canton, told Bosnian media despite recent poor weather construction of the road is proceeding. Cost of the six-kilometre double-tube tunnel will be around €92 million with phase one amounting to nearly €36 million. The tunnel will cut the journey between the two towns from 95km to 56km and the time from 90 minutes to 45 minutes.
  • Mozambique’ new bridge opens to traffic
    November 14, 2018
    Mozambique’s new suspension bridge connecting Maputo with Catembe is now open to traffic. The suspension bridge is the longest of its type in Africa, measuring almost 3km-long and surpassing the previous holder of this accolade, the Mapati Bridge in the Democratic Republic of Congo. The new bridge spans Maputo Bay and forms part of a new highway connection running from Mozambique’s capital, Maputo, all the way to the border with South Africa. The route will be of major benefit for Mozambique, helping to boo
  • Argentina road contract awarded
    October 20, 2017
    Argentina’s Route 33 is set to benefit from a major upgrade with the award of a contract to a consortium comprising local construction companies. The firms, Jose Cartellone Construcciones Civiles and Supercemento Saic, won the tender for the work with a bid worth US$198.5 million. The consortium will carry out construction work on a 70km section of Route 33 between Rosario and Rufino. Work is now commencing and should take around 24 months to complete. In all this stretch of the road measures 230km and addi
  • Major German road contract awarded
    September 2, 2020
    A major road contract has been awarded close to Hesse in Germany.