Strabag closes in on Poland’s S8 Marki-Kobylka contract

Strabag has nudged into the lead for Poland’s retender of the dual lane S8 section between the Marki and Kobylka junctions, previously held by Salini-Impreglio. Five offers were on the table for the deal with Strabag offering €38 million, well above the €32 million that was budgeted for by GDDKiA, Poland’s road authority. Other bids came from a consortium headed by Warszawskie Przedsiebiorstwo Mostowe Mosty at nearly €40 million, a PORR and Unibep consortium offere at almost €59 million, a bid by I
August 19, 2019 Read time: 2 mins
945 Strabag has nudged into the lead for Poland’s retender of the dual lane S8 section between the Marki and Kobylka junctions, previously held by Salini-Impreglio.  


Five offers were on the table for the deal with Strabag offering €38 million, well above the €32 million that was budgeted for by 1361 GDDKiA, Poland’s road authority.

Other bids came from a consortium headed by Warszawskie Przedsiebiorstwo Mostowe Mosty at nearly €40 million, a PORR and Unibep consortium offere at almost €59 million, a bid by Intercor at nearly €65 million and one by and Budimex at just over €39 million.

GDDKiA expects to sign a contract in November with completion set for spring 2021.
 
The contract is one two that make up construction of a 15km section of the S8 expressway. The consortium from Salini was responsible for the implementation of the first contract. The second has already been completed.

More than 500km of the planned 565km S8 road have been built since construction started in 2003. It runs from Wrocław to Białystok via Łódź and the capital Warsaw.

Originally, the road was to continue to the border with Lithuania, but in 2009 the plans were changed and currently the S61 will branch off the S8 and go to the border.

The S8 section from Warsaw to the S61 interchange is planned to become part of the Via Baltica, a stretch of the European route E 67.

Via Baltica runs from the Czech Republic to Helsinki in Finland by way of Poland, Lithuania, Latvia and Estonia. It goes via Prague, Wrocław, Warsaw, Kaunas, Panevėžys, Riga, Tallinn and Helsinki. The final stretch between the Estonian capital Tallinn and the Finnish capital Helsinki is by ferry, a two-and-a-half hour crossing of the Gulf of Finland.

For more information on companies in this article

Related Content

  • Strabag wins Polish A1 motorway deal for Wozniki-to-Pyrzowice section
    September 2, 2015
    Strabag consortium has signed a contract for construction of a 15.2km section of the A1 motorway between Wozniki and Pyrzowice. Completion of the section that will connect Pyrzowice with Czestochowa is due by the end of 2018. It is the first of four contracts signed for construction of the motorway. Strabag’s offer is believed to be around €144 million, while the budget set by the General Directorate for National Roads and Motorways (GDDKiA), was set just over €200 million. Meanwhile, the S6 dual car
  • Poland is planning a series of highway projects
    March 15, 2013
    Poland’s Ministry of Transport plans to invest heavily in road projects from 2014-2020. The Polish road authority, GDDKiA, will invest €16.91 billion in new roads. A key project will be for the section of the Berlin-Lisbon A2 highway that runs through Poland. This will run through Zakret near Warsaw and connect to the Minsk Mazowiecki ring road and is expected to cost close to €1.7 billion. Meanwhile the A1 highway linking Pyrzowice and Tuszyn will cost in excess of €1.8 billion. GDDKiA is also planning to
  • STRABAG building two more Polish routes
    January 12, 2018
    Contractor STRABAG has won deals to construct two more sections of the S7 route in Poland for some €198 million. The firm will build a total of 36km of the S7 route to the north of capital Warsaw. The construction work for the four lane route is expected to take 34 months to complete. One stretch runs from Strzegowo to Pieńki and is 22km long, the other stretch is 14km long and runs from Pieńki to Płońsk. The package of works also includes the construction of several junctions and rest areas as well as
  • Seven bids submitted for Croatia’s Peljeski bridge access roads
    June 18, 2018
    Croatia’s construction company Integral Inzinjering has submitted the lowest bid of €43 million for construction of access roads for the Peljeski bridge project. Croatian daily newspaper Vecernji List reported that seven bidsd were submitted for the 12.4km project. Highest bid of €88 million has come from China Road and Bridge Corporation, which has the contract to build the bridge. Austria's Strabag offered €65 million. Other bidders were France's Colas, Croatia's GP Krk in cooperation with the Bosni