A slow start for Mexico’s Atizapan-Atlacomulco highway

Almost one year after work started on Mexico’s Atizapan-Atlacomulco highway, little progress appears to have been made. OHL Mexico, a subsidiary of the Spanish construction firm OHL group -- Obrascon Huarte Lain -- said that the apparent lack of progress is due to the government not having arranged access to the road. Sergio Hidalgo, director general for OHL Mexico, told investors that the land for the first of three stages of the project, covering 25km between Atlacomulco and Ixtlahuaca was released
June 9, 2015 Read time: 2 mins
Almost one year after work started on Mexico’s Atizapan-Atlacomulco highway, little progress appears to have been made.

5494 OHL Mexico, a subsidiary of the Spanish construction firm OHL group -- Obrascon Huarte Lain -- said that the apparent lack of progress is due to the government not having arranged access to the road.

Sergio Hidalgo, director general for OHL Mexico, told investors that the land for the first of three stages of the project, covering 25km between Atlacomulco and Ixtlahuaca was released only in the first part of this year. Because of this late release, construction work can begin earliest this summer.

But the secretary of communications and transport has argued that OHL could have started work months ago. The government indicated that 53% of the land for the project has been released so far, providing sufficient area for work to start. The highway will cover 74km, with OHL's contract valid for 30 years, expiring in 2044.

OHL Mexico won the contract to build and operate the 74km road in central in March last year. The road will link Mexico's capital Mexico City and the western city of Guadalajara. The deadline for the highway to begin operating was originally May 15 2016.

OHL Mexico beat out infrastructure-development company 4881 Impulsora del Desarrollo y el Empleo en America Latina (IDEAL), owned by Mexican multi-billionaire Carlos Slim. OHL reportedly offered to build the highway for $449 million and to charge a standard toll per vehicle of $11.30 for the entire route.

Media reports said IDEAL offered to build the road $512.2 million and charge a toll of $10.70 per vehicle.

For more information on companies in this article

Related Content

  • Mexico’s road crisis from poor maintenance
    May 5, 2017
    Mexico’s road network is suffering a crisis due to a sustained period of poor maintenance and underfunding. This is the finding of the Mexican Secretariat of Communications and Transport (SCT). Its report reveals that almost 113,000km of the country’s federal road system, around 30% of the entire network, is in need of repairs or upgrades. Poor road conditions have slowed vehicle speeds on the network and also been the cause of crashes, an issue SCT is keen to alleviate. However the combination of insuffici
  • Mexican highway works underway
    September 15, 2021
    Key Mexican highway works are underway.
  • Julián Núñez, head of ASECAP offers a little Spanish enlightenment
    May 1, 2018
    Julián Núñez, president of ASECAP, gets his teeth into the vision of a European strategy for toll roads. David Arminas reports from Madrid Getting European politicians to agree to a long-term cross-border highway infrastructure programme for toll roads is extremely difficult. It’s a bit like pulling teeth. People want to avoid the pain. This is perhaps a bad analogy to use in the case of Julián Núñez, president of ASECAP - European Association of Operators of Toll Road Infrastructures. Núñez had just sat
  • Mexico highway funding package secured by OHL
    October 4, 2017
    Funding has been found to help pay for building and operating Mexico’s Atizapan-Atlacomulco highway. OHL is building the link and has secured US$364.6 million in loans for the project. The financing package is being provided by several banks, including Santander, Institucion de Banca Multiple, Banco Nacional de Obras y Servicios Publicos (Banobras) and Santander Mexico.