A slow start for Mexico’s Atizapan-Atlacomulco highway

Almost one year after work started on Mexico’s Atizapan-Atlacomulco highway, little progress appears to have been made. OHL Mexico, a subsidiary of the Spanish construction firm OHL group -- Obrascon Huarte Lain -- said that the apparent lack of progress is due to the government not having arranged access to the road. Sergio Hidalgo, director general for OHL Mexico, told investors that the land for the first of three stages of the project, covering 25km between Atlacomulco and Ixtlahuaca was released
June 9, 2015 Read time: 2 mins
Almost one year after work started on Mexico’s Atizapan-Atlacomulco highway, little progress appears to have been made.

5494 OHL Mexico, a subsidiary of the Spanish construction firm OHL group -- Obrascon Huarte Lain -- said that the apparent lack of progress is due to the government not having arranged access to the road.

Sergio Hidalgo, director general for OHL Mexico, told investors that the land for the first of three stages of the project, covering 25km between Atlacomulco and Ixtlahuaca was released only in the first part of this year. Because of this late release, construction work can begin earliest this summer.

But the secretary of communications and transport has argued that OHL could have started work months ago. The government indicated that 53% of the land for the project has been released so far, providing sufficient area for work to start. The highway will cover 74km, with OHL's contract valid for 30 years, expiring in 2044.

OHL Mexico won the contract to build and operate the 74km road in central in March last year. The road will link Mexico's capital Mexico City and the western city of Guadalajara. The deadline for the highway to begin operating was originally May 15 2016.

OHL Mexico beat out infrastructure-development company 4881 Impulsora del Desarrollo y el Empleo en America Latina (IDEAL), owned by Mexican multi-billionaire Carlos Slim. OHL reportedly offered to build the highway for $449 million and to charge a standard toll per vehicle of $11.30 for the entire route.

Media reports said IDEAL offered to build the road $512.2 million and charge a toll of $10.70 per vehicle.

For more information on companies in this article

Related Content

  • Autostrade del Lazio awards Sacyr company SIS the Roma-Latina deal
    July 15, 2016
    SIS, a subsidiary of Spanish contractor Sacyr, has won a €2.8 billion contract to build and operate the 186km Roma-Latina motorway in Italy. Autostrade Del Lazio, a public company created to build and manage the motorway, awarded the public private partnership contract, officially called Corridoio intermodale Roma-Latina e collegamento Cisterna-Valmontone. The SIS Scpa consortium, which consists of Sacyr (49%) and Fininc di Torino (51%), will build-operate-maintain the highway over 50 years. Revenue i
  • New highway for Mexico’s Baja
    November 13, 2015
    Work is now underway on a new highway in Mexico’s Baja California State. The Mexican Secretariat of Communications and Transport (SCT) has invested US$148.7 million in building the new Cabo San Lucas-San Jose del Cabo highway. The 38.7km project will include the construction of Caduano Bridge, the renovation and expansion of the Santa Rosa-Puerto Chale road and road surfacing at Todos Santos municipality.
  • Road pricing revenue a source of investment funds
    February 16, 2012
    When channelled back into the road sector, revenue from road charging is seen by many as a source of additional investment and research funds as Patrick Smith reports. Late in 2010, three major European organisations put out a policy statement calling for fair charging for greener, smarter and safer road infrastructure. ASECAP (the European toll road operators organisation); ERF (European Road Federation) and the IRU (International Road Transport Union), said that in recent years the concept of road chargin
  • New stretch of Mexico highway open to traffic
    August 1, 2016
    A 25km section of Guadalajara’s new bypass route in Mexico’s Jalisco State is now open to traffic. This section of the route cost just under US$81 million to construct. The bypass section features four lanes, with two in either direction and will help cut congestion in the centre of Guadalajara, as through-traffic will no longer have to drive into the city. The route is being built by Grupo Ideal and should be complete by December 2016. Once fully open for traffic, it will cut journey times in the area arou