Slovakia keeps to planned D1 Hubova-Ivachnova completion date

Slovakia’s national motorway company NDS has confirmed the D1 motorway between Hubova and Ivachnova is on schedule to be completed by mid-2022. Work on the 15km stretch of road – effectively a bypass for the town of Ruzomberok –was started in 2013. But a major landslide in 2015 halted work, pushing back completion from 2017 to 2022 at the latest estimate. Montenegrin media report that the cost of the project has grown from €227 million in 2013 to nearly €289 million. Construction is being carried out
August 19, 2019 Read time: 2 mins
Slovakia’s national motorway company 5891 NDS has confirmed the D1 motorway between Hubova and Ivachnova is on schedule to be completed by mid-2022.


Work on the 15km stretch of road – effectively a bypass for the town of Ruzomberok –was started in 2013. But a major landslide in 2015 halted work, pushing back completion from 2017 to 2022 at the latest estimate.

Slovakian media report that the cost of the project has grown from €227 million in 2013 to nearly €289 million. Construction is being carried out by the consortium Cebrat, comprising Vahostav-Sk and the Czech firm OHL ZS.

This project will connect the D1 Turany-Hubová highway on the west side and the D1 Ivachnova-Hybe section on the east side. Therefore, this project is key to the overall completion of a complete D1 motorway.

The 515km cross-country D1 connects the capital Bratislava, along the Danube River close the country’s western border with the Czech Republic, and in the eastern city of Košice. An extension is proposed from Košice to Michalovce, further east and closer to Slovakia’s eastern border with the Ukraine.

With the exceptions of sections in Bratislava, a vignette is required to use the motorway which also forms part of the European routes: E50, E58, E75 and E571.

For more information on companies in this article

Related Content

  • Slovakia's D1 highway moving ahead
    March 1, 2012
    Slovakia's Transport Ministry has been working with highway firm NDS on a highway construction programme for the 2011-2014 period.
  • Vahostav-SK and TuCon to build Slovakia’s Presov northern bypass
    July 4, 2019
    Slovak contractors Vahostav-SK and TuCon will build the first stage of the 4.3km northern bypass in Presov on the R4 dual carriageway. The contract was awarded in an open tender by Slovakia’s motorway company NDS. The consortium offered the lowest price of just under €143 million against around €170 million as estimated by NDS which says work will start this summer. NDS also said that it had received five firm bids for the work which will likely take three years and nine months, for completion in 2
  • Slovakia’s Ruzomberok bypass and tunnel face severer delays
    September 4, 2017
    The bypass around the Slovakian town of Ružomberok, which was supposed to be finished this summer, faces a delay of more than four years. The bypass is part of a 15.2km stretch of the D1 highway between Hubová and Ivachnová. Ružomberok, with a population of around 45,000 including its surrounding area, is in the Liptove region in northern Slovakia. It lies around 260km from the Slovakian capital Bratislava.
  • Delays ahead for Slovakia’s Visnove tunnel
    September 5, 2018
    Slovakia's transport ministry says the 7.5km Visnove tunnel near Zilina, part of the D1 motorway, will be delayed by two years to open in 2022. The recent announcement came as the ministry agreed to an extension to the construction permit held by Salini Impregilo for work on the twin-tube tunnel. The design-and-build contract worth about €410 million was assigned to the Salini Impregilo-led joint venture DUHA in 2014 by the National Highway Company NDS.