Slovakia keeps to planned D1 Hubova-Ivachnova completion date

Slovakia’s national motorway company NDS has confirmed the D1 motorway between Hubova and Ivachnova is on schedule to be completed by mid-2022. Work on the 15km stretch of road – effectively a bypass for the town of Ruzomberok –was started in 2013. But a major landslide in 2015 halted work, pushing back completion from 2017 to 2022 at the latest estimate. Montenegrin media report that the cost of the project has grown from €227 million in 2013 to nearly €289 million. Construction is being carried out
August 19, 2019 Read time: 2 mins
Slovakia’s national motorway company 5891 NDS has confirmed the D1 motorway between Hubova and Ivachnova is on schedule to be completed by mid-2022.


Work on the 15km stretch of road – effectively a bypass for the town of Ruzomberok –was started in 2013. But a major landslide in 2015 halted work, pushing back completion from 2017 to 2022 at the latest estimate.

Slovakian media report that the cost of the project has grown from €227 million in 2013 to nearly €289 million. Construction is being carried out by the consortium Cebrat, comprising Vahostav-Sk and the Czech firm OHL ZS.

This project will connect the D1 Turany-Hubová highway on the west side and the D1 Ivachnova-Hybe section on the east side. Therefore, this project is key to the overall completion of a complete D1 motorway.

The 515km cross-country D1 connects the capital Bratislava, along the Danube River close the country’s western border with the Czech Republic, and in the eastern city of Košice. An extension is proposed from Košice to Michalovce, further east and closer to Slovakia’s eastern border with the Ukraine.

With the exceptions of sections in Bratislava, a vignette is required to use the motorway which also forms part of the European routes: E50, E58, E75 and E571.

For more information on companies in this article

Related Content

  • Slovakia’s Parliament gives green light for e-toll law
    December 2, 2013
    Slovakia's Parliament has approved the new law on e-toll, replacing the use of traditional motorway stickers with electronic ones. The new regulation will come into force on 1 January 2015. The price of the motorway stickers, which motorists will be able to purchase online or through petrol stations, will not increase. The Transport Ministry intends to call the tender for the provider of the virtual vignettes within the next few weeks. In 2013, the national motorway company NDS printed more than 3.3 million
  • Slovakian highway projects delayed
    May 13, 2021
    Two Slovakian highway projects are now delayed.
  • Strasbourg bypass surveys halted over environmental concerns
    September 27, 2017
    Further delays are looming for construction of the western Strasbourg bypass, a controversial toll motorway project in north eastern France. The government is concerned about environmental issues after Arcos, the wholly-owned subsidiary of Vinci responsible for building the bypass, said it was going to carry out field surveys in 1.5 hectares of what many consider environmentally sensitive areas.
  • Czech tenders for section of D11, part of the E67 Via Baltica
    July 15, 2016
    The Czech road management company RSD is seeking a contractor for construction of 15km of the D11 motorway between Hradec Kralove and Smirice. Both towns are in northern Czech Republic, near the Polish border. The work is worth around €218.3 million, according to Czech media, and is one of the last remaining sections of the D11 to be built. Construction of another section between the town of Trutnov and the border with Poland is likely to start in 2019 and the Jaromer-Trutnov section after 2020.