Slovakia keeps to planned D1 Hubova-Ivachnova completion date

Slovakia’s national motorway company NDS has confirmed the D1 motorway between Hubova and Ivachnova is on schedule to be completed by mid-2022. Work on the 15km stretch of road – effectively a bypass for the town of Ruzomberok –was started in 2013. But a major landslide in 2015 halted work, pushing back completion from 2017 to 2022 at the latest estimate. Montenegrin media report that the cost of the project has grown from €227 million in 2013 to nearly €289 million. Construction is being carried out
August 19, 2019 Read time: 2 mins
Slovakia’s national motorway company 5891 NDS has confirmed the D1 motorway between Hubova and Ivachnova is on schedule to be completed by mid-2022.


Work on the 15km stretch of road – effectively a bypass for the town of Ruzomberok –was started in 2013. But a major landslide in 2015 halted work, pushing back completion from 2017 to 2022 at the latest estimate.

Slovakian media report that the cost of the project has grown from €227 million in 2013 to nearly €289 million. Construction is being carried out by the consortium Cebrat, comprising Vahostav-Sk and the Czech firm OHL ZS.

This project will connect the D1 Turany-Hubová highway on the west side and the D1 Ivachnova-Hybe section on the east side. Therefore, this project is key to the overall completion of a complete D1 motorway.

The 515km cross-country D1 connects the capital Bratislava, along the Danube River close the country’s western border with the Czech Republic, and in the eastern city of Košice. An extension is proposed from Košice to Michalovce, further east and closer to Slovakia’s eastern border with the Ukraine.

With the exceptions of sections in Bratislava, a vignette is required to use the motorway which also forms part of the European routes: E50, E58, E75 and E571.

For more information on companies in this article

Related Content

  • Work starts on Komarno-Komarom Bridge between Slovakia and Hungary
    October 31, 2017
    Construction has started on the €117 million bridge over the Danube River between the Hungarian town of Komarom and the Slovak town of Komarno. Around 85% of the cost will be covered by European Union’s Connecting Europe Facility. Completion is planned for winter 2019. Last summer it was announced that the Hungarian companies Hidepito and Meszaros es Meszaros had won the tender for the 600m bridge but with a price tag of just over €91 million, according to Hungarian media. It was also reported at the time
  • Slovakia’s new highway tenders opening
    November 15, 2024
    Slovakia is opening new highway tenders to bidders.
  • Upgrade of Slovakia’s busy D1 stretch to start in H2 2014
    March 19, 2014
    Slovak national motorway company NDS plans to start the reconstruction and modernisation of the D1 motorway section between Bratislava and Trnava in H2 2014. As part of the near €150 million project, the current six-lane motorway will be extended by adding an emergency lane. The building works are expected to last 24 months and will include demolition and reconstruction of some of the existing road bridges, as well as construction of new ones. The motorway lanes will be extended from the current 3.5m to 3.
  • Slovakian road tunnel plan
    January 18, 2023
    Slovakia’s new road tunnel is being planned.