Slovakia keeps to planned D1 Hubova-Ivachnova completion date

Slovakia’s national motorway company NDS has confirmed the D1 motorway between Hubova and Ivachnova is on schedule to be completed by mid-2022. Work on the 15km stretch of road – effectively a bypass for the town of Ruzomberok –was started in 2013. But a major landslide in 2015 halted work, pushing back completion from 2017 to 2022 at the latest estimate. Montenegrin media report that the cost of the project has grown from €227 million in 2013 to nearly €289 million. Construction is being carried out
August 19, 2019 Read time: 2 mins
Slovakia’s national motorway company 5891 NDS has confirmed the D1 motorway between Hubova and Ivachnova is on schedule to be completed by mid-2022.


Work on the 15km stretch of road – effectively a bypass for the town of Ruzomberok –was started in 2013. But a major landslide in 2015 halted work, pushing back completion from 2017 to 2022 at the latest estimate.

Slovakian media report that the cost of the project has grown from €227 million in 2013 to nearly €289 million. Construction is being carried out by the consortium Cebrat, comprising Vahostav-Sk and the Czech firm OHL ZS.

This project will connect the D1 Turany-Hubová highway on the west side and the D1 Ivachnova-Hybe section on the east side. Therefore, this project is key to the overall completion of a complete D1 motorway.

The 515km cross-country D1 connects the capital Bratislava, along the Danube River close the country’s western border with the Czech Republic, and in the eastern city of Košice. An extension is proposed from Košice to Michalovce, further east and closer to Slovakia’s eastern border with the Ukraine.

With the exceptions of sections in Bratislava, a vignette is required to use the motorway which also forms part of the European routes: E50, E58, E75 and E571.

For more information on companies in this article

Related Content

  • Budimir-Bidovce section of Slovakia D1 motorway link could begin in 2014
    October 15, 2012
    The construction of the 14.4km D1 motorway stretch between Budimir - Bidovce near Kosice in eastern Slovakia could begin in 2014 or 2015. Building works for the Budimir-Bidovce D1 route should take three years, followed by the construction of another stretch of the D1 from Bidovce up to the Ukrainian border. The latter works are estimated for completion sometime after 2020. Meanwhile, the construction of the 13km D1 stretch linking Bidovce - Dargov and the 18.7km stretch Dargov - Pozdisovce should start in
  • Slovakia’s Budimir-Bidovce motorway stretch to open by December
    June 25, 2019
    Slovakia’s 14km stretch of the east-west motorway D1, from Bidovce to Budimir, will open in December, according to the government. Last year, Slovakia’s motorway company NDS and the transport ministry agreed a subsidy of nearly €204 million for the D1 section. The EU is covering 85% of the project cost, while the remaining 15% is covered by the government for construction the Budimir-to-Bidovce stretch, near the city of Kosice. The section, being built by Skanska for almost €237 million, is part of th
  • Poland tenders for Czestochowa A1 motorway section
    June 18, 2019
    Poland’s General Directorate for National Roads and Motorways (GDDKiA) reports that that the three bids for the Czestochowa A1 motorway section exceed the agency’s budget. The least expensive bid was nearly €101 million, submitted by a consortium of Strabag Infrastruktura Poludnie, Budimex and Budpol. Lemar bid around €121 million while Intercor bid €159 million. GDDKiA said that the bids will not automatically be rejected. Earlier this year GDDKiA terminated its contract with Salini Polska, signed
  • Bids for Višňové Tunnel's IT being evaluated
    March 31, 2023
    The contract, in Slovakia, also includes IT equipment for the D1 motorway stretch Lietavska Lucka - Visnove - Dubna Skala of which the tunnel is a part.