Slovakia: early 2017 restart for work on the Cebrat Tunnel

Roman Brecely, Slovakia’s transport minister, has said that construction of the 2km long motorway tunnel Cebrat near Ruzomberok could be resumed at the beginning of 2017. But the cost is expected to increase by around €100 million. He added that the government likely will seek European Union funding. Construction was halted a year ago over concerns about the possibility of landslides and other geological issues. For this reason, the tunnel route may alter and be an additional 1.5km longer. The tunn
May 27, 2016 Read time: 2 mins
Roman Brecely, Slovakia’s transport minister, has said that construction of the 2km long motorway tunnel Cebrat near Ruzomberok could be resumed at the beginning of 2017.

But the cost is expected to increase by around €100 million. He added that the government likely will seek European Union funding.

Construction was halted a year ago over concerns about the possibility of landslides and other geological issues. For this reason, the tunnel route may alter and be an additional 1.5km longer.

The tunnel is part of the D1 motorway section between Hubova and Ivachvova, which was supposed to be completed in June next year but will probably be completed in 2020.

Brecely also recently said that delays could affect construction of three motorway stretches, one section of the D3 and two of the D1.

Meanwhile the state-owned national motorway company 5891 NDS said that some 87% of land needed for the public-private partnership Bratislava Bypass has been expropriated. Construction is about to start on one section of the Bratislava bypass after the contract was finally sealed with the consortium Obchvat Nula (Bypass Zero), led by 930 Cintra of Spain and including 2378 Macquarie from Australia and 3976 Porr of Austria.

Media reports said that Cintra has 12 weeks to secure financing for the 30-year public-private partnership likely to cost upwards of €1.9 billion.

For more information on companies in this article

Related Content

  • Bids for Višňové Tunnel's IT being evaluated
    March 31, 2023
    The contract, in Slovakia, also includes IT equipment for the D1 motorway stretch Lietavska Lucka - Visnove - Dubna Skala of which the tunnel is a part.
  • Delays ahead for Slovakia’s Visnove tunnel
    September 5, 2018
    Slovakia's transport ministry says the 7.5km Visnove tunnel near Zilina, part of the D1 motorway, will be delayed by two years to open in 2022. The recent announcement came as the ministry agreed to an extension to the construction permit held by Salini Impregilo for work on the twin-tube tunnel. The design-and-build contract worth about €410 million was assigned to the Salini Impregilo-led joint venture DUHA in 2014 by the National Highway Company NDS.
  • Date set to complete D1 Višňové Tunnel section
    July 20, 2023
    The D1 section between Lietavská Lúčka and Dubná Skala in Slovakia includes the partially completed 7.5km twin-tube Višňové Tunnel - to be the country's longest.
  • Go-ahead for controversial highway
    May 30, 2012
    APPROVAL HAS now been given for work to go ahead on a key section of Slovakia’s D1 highway. The work had been delayed as the European Commission (EC) was concerned over environmental issues facing sections of the route that passed through a nature reserve. The EC has now given its approval for construction of the highway between Martin and Presov on conditional terms. The EC says that the sections in zones belonging to the Natura 2000 network can be built once terms are agreed with the Slovak government o