Slovakia: early 2017 restart for work on the Cebrat Tunnel

Roman Brecely, Slovakia’s transport minister, has said that construction of the 2km long motorway tunnel Cebrat near Ruzomberok could be resumed at the beginning of 2017. But the cost is expected to increase by around €100 million. He added that the government likely will seek European Union funding. Construction was halted a year ago over concerns about the possibility of landslides and other geological issues. For this reason, the tunnel route may alter and be an additional 1.5km longer. The tunn
May 27, 2016 Read time: 2 mins
Roman Brecely, Slovakia’s transport minister, has said that construction of the 2km long motorway tunnel Cebrat near Ruzomberok could be resumed at the beginning of 2017.

But the cost is expected to increase by around €100 million. He added that the government likely will seek European Union funding.

Construction was halted a year ago over concerns about the possibility of landslides and other geological issues. For this reason, the tunnel route may alter and be an additional 1.5km longer.

The tunnel is part of the D1 motorway section between Hubova and Ivachvova, which was supposed to be completed in June next year but will probably be completed in 2020.

Brecely also recently said that delays could affect construction of three motorway stretches, one section of the D3 and two of the D1.

Meanwhile the state-owned national motorway company 5891 NDS said that some 87% of land needed for the public-private partnership Bratislava Bypass has been expropriated. Construction is about to start on one section of the Bratislava bypass after the contract was finally sealed with the consortium Obchvat Nula (Bypass Zero), led by 930 Cintra of Spain and including 2378 Macquarie from Australia and 3976 Porr of Austria.

Media reports said that Cintra has 12 weeks to secure financing for the 30-year public-private partnership likely to cost upwards of €1.9 billion.

For more information on companies in this article

Related Content

  • Bosnia cancels a tender for Corridor 5C, part of European route E73
    March 13, 2017
    Bosnia is cancelling a tender for part of its Corridor 5C project, an integral part of the class-A north-south central European route E73. Route E73 runs around 700km from Hungary south through eastern Croatia to Bosnia and Herzegovina and the Adriatic Sea in the area of Ploče port. The longest part of this corridor goes through Bosnia and Herzegovina – nearly 340km. Director of the Bosnian motorways company Autoput FBiH, Adnan Terzic, confirmed the cancelled tender to the Bosnian daily newspaper Dnev
  • Quebec to build new Mercier Bridge for Montreal city
    May 12, 2017
    The Canadian province of Quebec plans to build a US$219 million bridge across the St Lawrence River alongside the existing Mercier Bridge in the city of Montreal. Provincial government cabinet ministers Pierre Moreau and Geoff Kelley confirmed that a new bridge is forthcoming, but gave schedule for procurement or construction start, according to local media. However, Moreau said the work will begin probably before the new Champlain Bridge is finished at the start of 2019. Construction of the new Champlain B
  • Lueg Bridge work sparks congestion fears
    June 23, 2022
    Lueg Bridge, along Austria’s section of the Brenner Pass route, is slated for major rehabilitation work as part of upgrades to the tolled motorway.
  • Danish-German Fehmarn Belt road and rail tunnel hits funding snag
    July 9, 2015
    A Danish newspaper has learned of a significant European Union funding gap for one of Europe’s most ambitious transportation road and rail projects. The Fehmarn Belt Fixed Link would connect the German island of Fehmarn with the Danish island of Lolland. A submersed tunnel will cross the 18km-wide Fehmarn Belt, or Fehmarn Strait, in the Baltic Sea. Last February news emerged that contractors had revamped their cost estimates, adding nearly €1.2 billion to the project. This put the final cost of the 18