Slovakia: early 2017 restart for work on the Cebrat Tunnel

Roman Brecely, Slovakia’s transport minister, has said that construction of the 2km long motorway tunnel Cebrat near Ruzomberok could be resumed at the beginning of 2017. But the cost is expected to increase by around €100 million. He added that the government likely will seek European Union funding. Construction was halted a year ago over concerns about the possibility of landslides and other geological issues. For this reason, the tunnel route may alter and be an additional 1.5km longer. The tunn
May 27, 2016 Read time: 2 mins
Roman Brecely, Slovakia’s transport minister, has said that construction of the 2km long motorway tunnel Cebrat near Ruzomberok could be resumed at the beginning of 2017.

But the cost is expected to increase by around €100 million. He added that the government likely will seek European Union funding.

Construction was halted a year ago over concerns about the possibility of landslides and other geological issues. For this reason, the tunnel route may alter and be an additional 1.5km longer.

The tunnel is part of the D1 motorway section between Hubova and Ivachvova, which was supposed to be completed in June next year but will probably be completed in 2020.

Brecely also recently said that delays could affect construction of three motorway stretches, one section of the D3 and two of the D1.

Meanwhile the state-owned national motorway company 5891 NDS said that some 87% of land needed for the public-private partnership Bratislava Bypass has been expropriated. Construction is about to start on one section of the Bratislava bypass after the contract was finally sealed with the consortium Obchvat Nula (Bypass Zero), led by 930 Cintra of Spain and including 2378 Macquarie from Australia and 3976 Porr of Austria.

Media reports said that Cintra has 12 weeks to secure financing for the 30-year public-private partnership likely to cost upwards of €1.9 billion.

For more information on companies in this article

Related Content

  • Komarno bridge on schedule despite cost and environmental protests
    July 13, 2018
    Slovakia’s transport minister said he will do everything possible to finish on time a new bridge connecting Komano with the Hungarian town of Komarom. Construction started last year on the €117 million bridge over the Danube River between the Hungarian town of Komarom and the Slovak town of Komarno. Around 85% of the cost of the bridge - designed by Hungarian engineering firm Pont-Terv - will be covered by European Union’s Connecting Europe Facility. Completion is planned for winter 2019. Transport m
  • Komarno bridge on schedule despite cost and environmental protests
    July 13, 2018
    Slovakia’s transport minister said he will do everything possible to finish on time a new bridge connecting Komano with the Hungarian town of Komarom. Construction started last year on the €117 million bridge over the Danube River between the Hungarian town of Komarom and the Slovak town of Komarno. Around 85% of the cost of the bridge - designed by Hungarian engineering firm Pont-Terv - will be covered by European Union’s Connecting Europe Facility. Completion is planned for winter 2019. Transport m
  • Slovakia’s R2 Expressway moves a step closer
    June 4, 2018
    Slovakia said it will tender this year for the 14km R2 expressway linking Roznava and Jablonov nad Turnov with completion likely in 2024. Slovakia's transport minister Arpad Ersek said construction could start by Q3 2019. R2 is a 360km route that will run from Kosice in the east across the country to Trenčín, near the Czech border in the west. It will pass through Bánovce nad Bebravou, Prievidza and Lučenec. Roznava is an economic and tourist centre around 70km from Kosice.
  • Czech road project awards and tender
    July 19, 2024
    Czech road projects have been awarded, with another due to open for tender.