Slovakia: early 2017 restart for work on the Cebrat Tunnel

Roman Brecely, Slovakia’s transport minister, has said that construction of the 2km long motorway tunnel Cebrat near Ruzomberok could be resumed at the beginning of 2017. But the cost is expected to increase by around €100 million. He added that the government likely will seek European Union funding. Construction was halted a year ago over concerns about the possibility of landslides and other geological issues. For this reason, the tunnel route may alter and be an additional 1.5km longer. The tunn
May 27, 2016 Read time: 2 mins
Roman Brecely, Slovakia’s transport minister, has said that construction of the 2km long motorway tunnel Cebrat near Ruzomberok could be resumed at the beginning of 2017.

But the cost is expected to increase by around €100 million. He added that the government likely will seek European Union funding.

Construction was halted a year ago over concerns about the possibility of landslides and other geological issues. For this reason, the tunnel route may alter and be an additional 1.5km longer.

The tunnel is part of the D1 motorway section between Hubova and Ivachvova, which was supposed to be completed in June next year but will probably be completed in 2020.

Brecely also recently said that delays could affect construction of three motorway stretches, one section of the D3 and two of the D1.

Meanwhile the state-owned national motorway company 5891 NDS said that some 87% of land needed for the public-private partnership Bratislava Bypass has been expropriated. Construction is about to start on one section of the Bratislava bypass after the contract was finally sealed with the consortium Obchvat Nula (Bypass Zero), led by 930 Cintra of Spain and including 2378 Macquarie from Australia and 3976 Porr of Austria.

Media reports said that Cintra has 12 weeks to secure financing for the 30-year public-private partnership likely to cost upwards of €1.9 billion.

For more information on companies in this article

Related Content

  • Budimir-Bidovce section of Slovakia D1 motorway link could begin in 2014
    October 15, 2012
    The construction of the 14.4km D1 motorway stretch between Budimir - Bidovce near Kosice in eastern Slovakia could begin in 2014 or 2015. Building works for the Budimir-Bidovce D1 route should take three years, followed by the construction of another stretch of the D1 from Bidovce up to the Ukrainian border. The latter works are estimated for completion sometime after 2020. Meanwhile, the construction of the 13km D1 stretch linking Bidovce - Dargov and the 18.7km stretch Dargov - Pozdisovce should start in
  • Slovakian highway deal for Budimex
    November 2, 2022
    A Slovakian highway deal has been awarded to Budimex.
  • Private owners seek a buyer for the UK’s only toll road, M6 Toll
    February 15, 2016
    Britain’s only toll road, the motorway M6 Toll, is up for sale by its owners, a consortium of banks that hope to recover some of the €2.45 billion of debt. The 27 owners of M6 Toll, including Crédit Agricole, Commerzbank and Banco Espirito Santo, took over the 43km pay-as-you-go toll road from infrastructure group Macquarie in December 2013 after a debt restructuring. Midland Expressway Limited (MEL), part of Macquarie Atlas Roads, continues to operate the six-lane motorway around the English city of
  • New Slovakia highway opening for traffic
    November 26, 2015
    Stretches of a major new highway project in Slovakia are opening for traffic. Two sections of the D1 highway are opening by the end of 2015. Slovakian National Motorway Company has said that the second section of the 9.5km D1 highway stretch from Janovce-Jablonov, near the town of Levoca, will open by the end of 2015. The other section set to open will be the D1 stretch from Fricovce – Svinia and located near Presov. During 2015 NDS planned to open five new motorway stretches, of which three are already in