Slovakia: early 2017 restart for work on the Cebrat Tunnel

Roman Brecely, Slovakia’s transport minister, has said that construction of the 2km long motorway tunnel Cebrat near Ruzomberok could be resumed at the beginning of 2017. But the cost is expected to increase by around €100 million. He added that the government likely will seek European Union funding. Construction was halted a year ago over concerns about the possibility of landslides and other geological issues. For this reason, the tunnel route may alter and be an additional 1.5km longer. The tunn
May 27, 2016 Read time: 2 mins
Roman Brecely, Slovakia’s transport minister, has said that construction of the 2km long motorway tunnel Cebrat near Ruzomberok could be resumed at the beginning of 2017.

But the cost is expected to increase by around €100 million. He added that the government likely will seek European Union funding.

Construction was halted a year ago over concerns about the possibility of landslides and other geological issues. For this reason, the tunnel route may alter and be an additional 1.5km longer.

The tunnel is part of the D1 motorway section between Hubova and Ivachvova, which was supposed to be completed in June next year but will probably be completed in 2020.

Brecely also recently said that delays could affect construction of three motorway stretches, one section of the D3 and two of the D1.

Meanwhile the state-owned national motorway company 5891 NDS said that some 87% of land needed for the public-private partnership Bratislava Bypass has been expropriated. Construction is about to start on one section of the Bratislava bypass after the contract was finally sealed with the consortium Obchvat Nula (Bypass Zero), led by 930 Cintra of Spain and including 2378 Macquarie from Australia and 3976 Porr of Austria.

Media reports said that Cintra has 12 weeks to secure financing for the 30-year public-private partnership likely to cost upwards of €1.9 billion.

For more information on companies in this article

Related Content

  • Flyover and tunnel planned for D3 route in Slovakia
    February 13, 2015
    In Slovakia plans are in hand for work to the D3 route that will involve the construction of a flyover, a bridge and a tunnel. The flyover lies on the stretch of D3 between Zilina/Strazov and Zilina/Brodno. Work on this 4.25km section of the D3 is costing close to €255 million. The construction work commenced in June 2014 and is due for completion by 2017. The work is complex and includes building flyover over the Hricovska Prehrada Dam, as well as driving a tunnel and constructing bridge over the Kysuca Ri
  • Slovakian road tunnel plan
    January 18, 2023
    Slovakia’s new road tunnel is being planned.
  • Russia to commission new Moscow-St Petersburg highway by 2020
    June 20, 2017
    Final delivery of the final stretch for Russia’s key highway project looks set to be delayed – Eugene Gerden writes. I now looks as if Russia’s most ambitious project in the field of road building in recent years, the building of a new high-speed road link between Moscow and St Petersburg, the country’s largest cities, will not be complete in time. The project was set up by the Russian government and several private investors. According to initial state plans, building of the new road should have been compl
  • Tunnel Boom in Central and Eastern Europe
    September 15, 2015
    Following the success of the 41st World Tunnel Congress held in Croatia last May, World Highways looks at two signi_ cant projects in Slovakia and Serbia – Adriana Potts reports Central and Eastern Europe is buzzing with a number of major projects being developed - including highways, bridges and tunnels – and with many more in the pipeline. The region is expected to be highly active with plans for developing infrastructure in the next two decades, according to Davorin Koli , president of the Croatian