Serbia in talks with Chinese firms over Corridor 11 completion

Serbia will enter into talks with two Chinese companies chosen through a tender process that expired this month for restarting construction on the stalled Corridor 11 motorway. Serbian Minister of Construction Zorana Mihajlovic said Shandong Hi-Speed Group and the China Road and Bridge Corporation qualified for tender participation. Work includes construction and maintenance of 17.6km of motorway near Belgrade, between Surcin and Obrenovac as welll as the 31km Preljina-Pozega road and maintenance of t
February 12, 2015 Read time: 2 mins

Serbia will enter into talks with two Chinese companies chosen through a tender process that expired this month for restarting construction on the stalled Corridor 11 motorway.

Serbian Minister of Construction Zorana Mihajlovic said 3034 Shandong Hi-Speed Group and the 3366 China Road and Bridge Corporation qualified for tender participation.

Work includes construction and maintenance of 17.6km of motorway near Belgrade, between Surcin and Obrenovac as welll as the 31km Preljina-Pozega road and maintenance of the 103km Obrenovac-Preljina road.

The Belgrade-Pozega road will connect Serbia with Montenegro to the west and Romania to the east. China's Exim Bank approved a loan of €295.06 million for construction of the 50km road between Lajkovac and Ljig as well as Obrenovac and U, on Corridor 11.

Part of Corridor 11 was to be built under a concession awarded to the Austrian firm 2859 Alpine and Romanian company 3976 PORR, as well maintenance work for the Novi Sad-Belgrade highway. However, with the collapse of Alpine in mid-2013, the contract had to be renegotiated.

For more information on companies in this article

Related Content

  • Serbia speeding spending on roads
    May 21, 2014
    Serbia is planning to speed construction of its highway network. A key project being prioritised is the Corridor 10 motorway, which is due for completion by September 2016. Another priority project is for Corridor 11 and for several regional road routes. At present the Corridor 10 sections between Sid and Belgrade, and Subotica and Belgrade have been built, while work on the 22km Ipsilon stretch between Subotica and Kelebija is underway. Work is also underway on the 96km south node from Grabovnica to Presev
  • Work on Serbia’s Corridor 10 highway is on track
    April 3, 2014
    In Serbia work on the Corridor 10 highway looks set to be completed as planned in 2016. Serbian roads company, Koridori Srbije, says that that the Corridor 10 motorway should be completed by the middle of 2016. The World Bank (WB) mission visited building sites on Corridor 10 and said that considerable progress has been made, with an additional 23% of works having been carried out in the last 18 month period. In 2014 alone, 50km of the route will be completed. Work is being carried out on 238 bridges, out o
  • Serbia, Turkey formalise cooperation for Belgrade-Sarajevo motorway
    October 20, 2017
    Serbia has cemented its cooperation deal with Turkey for construction of the Belgrade-Sarajevo motorway at an estimated cost of around €830 million. The 60km motorway will be an extension of the Corridor 11 project and start where the 31km long Preljine-Pozega segment of Corridor 11 ends, Serbian media reported.
  • China to begin works on Serbia’s Corridor 11 motorway later this month
    August 27, 2013
    Chinese company Shandong High Speed Group is planning to begin construction works on Serbia’s Corridor 11 motorway in the second half of September 2013. Shandong will participate with 51% of works on the Lajkovac-Ljig and Obrenovac-Ub parts of the motorway, with domestic companies participating in the remainder of the works, due for completion within 38 months. Meanwhile, the Azerbaijan-based firm Azvirt is working on the 40km part of the Ljig-Preljina motorway, worth a total of €308 million.