Serbia ponders penalties for Azvirt over Ljig-Preljina delays

The Serbian government has said it could issue penalties to the Azerbaijani construction company Azvirt for delays to work on the Ljig-Preljina Corridor 11 motorway project. Completion was set for the middle of next month. But last month the government said delays of around a month were due to problems construction the tunnel and bridge sections. The new route is expected to open around 40 days later than originally expected as a result.
September 9, 2016 Read time: 1 min

The Serbian government has said it could issue penalties to the Azerbaijani construction company 5414 Azvirt for delays to work on the Ljig-Preljina Corridor 11 motorway project.

Completion was set for the middle of next month. But last month the government said delays of around a month were due to problems construction the tunnel and bridge sections. The new route is expected to open around 40 days later than originally expected as a result.

Minister of Transport, Zorana Mihajlovic, had stated that the government will want an explanation from the investor, Serbian roads company 3235 Koridori Srbije.

For more information on companies in this article

Related Content

  • Serbian highway plans
    March 19, 2012
    Serbian contractor Milos Trans will start work on the Serbia’s Corridor 11 highway during 2012. The firm will carry out work on the stretch running from Preljina to Takovo.
  • Serbia starts in-depth talks with the Chinese for Corridor 11 work
    May 7, 2015
    Serbia has entered into “in depth” negotiations with two Chinese companies for concession contracts along the Corridor 11 motorway between Belgrade and the Montenegrin border. Shandong High Speed Group and the China Road and Bridge Corporation (CRBC) are the two Chinese companies that have passed the pre-qualification process. The project value has not been mentioned. Serbian vice president Zorana Mihajlovic said that the Chinese have requested guarantees for transport and Serbia is considering this a
  • Serbia: Putevi Srbije to build 2.4km of Corridor 11 access road
    April 14, 2015
    Serbian road contractor Putevi Srbije will build around 2.4km of access roads around the town of Ljig in central Serbia, according the state Ministry of Construction, Transport and Infrastructure. The access roads will be for the Corridor 11 motorway, which is under construction from the Serbian capital Belgrade running southwest into Montenegro, ending at the Adriatic coastal tourist town of Bar. The Belgrade-Bar motorway will be around 280km long and be the main link for a ferry service from the Ita
  • Chinese firms to work on Serbia’s Corridor 11 project
    November 30, 2015
    Serbia and China have signed a memorandum of understanding for construction of two sections of Serbia’s Corridor 11. The MoU was inked in during Serbian Prime Minister Aleksandar Vucic’s visit to the Chinese capital Beijing last week. Serbia’s Tanjug news agency reported that Vucic said the deal was worth around €209 million and included construction of the 18km Surcin-Obrenovac bridge. Corridor 11 runs from the Serbian capital Belgrade southwest to the border with Montenegro, another member state of