Serbia: end in sight for finishing southern part of Corridor 10

Serbia’s minister of construction and infrastructure, Zorana Mihajlovic, said that the southern part of the Corridor 10 motorway is expected to be completed by the end of 2017. Speaking to the Beta news agency, she also said that work on the Corridor 11 motorway, on the Ub-Lajkovac section, is being carried out in cooperation with Chinese partner company Shang Dong. The government has also signed an agreement for construction of the Surcin-Obrenovac part of the Corridor 11. Ongoing talks between Serbi
August 26, 2016 Read time: 2 mins
Serbia’s minister of construction and infrastructure, Zorana Mihajlovic, said that the southern part of the Corridor 10 motorway is expected to be completed by the end of 2017.

Speaking to the Beta news agency, she also said that work on the Corridor 11 motorway, on the Ub-Lajkovac section, is being carried out in cooperation with Chinese partner company Shang Dong.

The government has also signed an agreement for construction of the Surcin-Obrenovac part of the Corridor 11. Ongoing talks between Serbia’s ministry of finance and China's Exim Bank should put financing in place by the end of this year.

Mihajlovic said that projects worth nearly €6 billion are underway. Corridor 10, towards Bulgaria and Macedonia, is one of the higher priority projects as well as the motorway towards the Montenegrin border on Corridor 11. Contracts include rehabilitation of around 1,100km of regional roads. The minister noted that Serbia aims to be on the World Bank's Top 20 Doing Business list.

Meanwhile, Zoran Drobnjak, director of the Serbian national roads company Putevi Srbije, said that he had order an investigation into the quality of the Zapadna Morava River Bridge Project. Work has been going on for around 40 years. According to a report by the online news website B92, Drobnjak said that there are questions over the amount of cement used by the sub-contracting companies Kes International from Hungary and Serbia's Vest Gradnja.

Related Content

  • Serbia says Corridor 10 completion to be delayed
    June 12, 2017
    Delays will hit Serbia’s Corridor 10 motorway project that was due for completion later this year. Serbia’s Minister of Construction, Zorana Mihajlovic, said that her department will soon publish as report on the delays, suggesting options for speeding up the work.
  • Serbia and Bosnia consider options for a Belgrade-Sarajevo project
    December 19, 2016
    Serbia and Bosnia have started talks on constructing a fast highway between the Serbian capital Belgrade and Sarajevo, capital of Bosnia and Herzegovina. Serbian Vice President Zorana Mihajlovic met with the Bosnian minister of transport, Ismir Jusko, to agree on forming a joint working group to consider routes and road construction, according to the Serbian newspaper B92. Mihajlovic said that Serbia's main focus is for building the 100km Pozega-Visegrad section, of which 60km is in Serbia and 40km in
  • Serbia approves merger of Koridori Srbije and Putevi Srbije
    November 25, 2014
    Serbia’s Ministry of Construction, Transport and Infrastructure has approved a merger between the public-owned roads companies Putevi Srbije (Roads of Serbia) and Koridori Srbije (Corridors of Serbia). Putevi Srbije maintains roads while Koridori focuses on construction planning and project management, including expropriation of land. The government said the merger will contribute to faster completion of projects such as stretches of Europe’s Corridor 10 and Corridor 11 road networks and hopefully red
  • Corridor 10 project in Serbia may be delayed
    April 2, 2013
    A series of challenges are now facing the project to construct Serbia’s key Corridor 10 highway. The EU has asked the Serbian Government for details of the priority plan and deadlines for the completion of the Corridor 10 highway. At present three sections of Corridor 10 are at risk, due to delays and financing issues. These are the Ciflik-Pirot stretch, the Bancarevo tunnel and the Vladicin Han section. According to Serbian roads company Koridori Srbije, the construction schedule will be set by the end of