A rough ride for Denmark’s National Road Directorate

Denmark’s National Audit Office has criticised the Danish National Road Directorate for consistently miscalculating the level of investment required for road projects. The Road Directorate – Vejdirektoratet - used 33% less than budgeted for road projects from 2007-2017. The audit office said that "budget calculations by the transport ministry, including the Road Directorate, have not been accurate enough". Jens Holmboe, head of the Road Directorate, rejected the criticism, saying that the Audit Office
November 1, 2019 Read time: 2 mins
Denmark is not spending enough? (Roskilde Bridge, photo courtesy RBAI joint venture)
Denmark’s 5285 National Audit Office has criticised the Danish National Road Directorate for consistently miscalculating the level of investment required for road projects.


The Road Directorate – Vejdirektoratet - used 33% less than budgeted for road projects from 2007-2017. The audit office said that "budget calculations by the transport ministry, including the Road Directorate, have not been accurate enough".

Jens Holmboe, head of the Road Directorate, rejected the criticism, saying that the Audit Office did not consider the effect the financial crisis had on building projects. The crisis resulted, among other things, in major price decreases for various road projects.

The Vejdirektoratet is responsible for the more than 1,200km of motorways, a number of main roads and many of the country's bridges – a total of about 4,000km. Denmark, being a country mainly of islands, relies on its bridges and tunnels to help unify the nation culturally. It also means that they are vastly more important to the economic well-being of the nation than in most other states.

In  mid-2015, Denmark became the first country in the world to rely on GPS probe data to monitor traffic and congestion on a national scale. It chose INRIX, a provider of transportation intelligence and connected car services, to set up a real-time traffic information system throughout the country. The directorate monitors traffic flow and gridlock across its entire national road network.

Early last year, an Italian joint venture won the construction contract for what will be one of Denmark’s longest bridges, the replacement 4km-long road and rail Storstrom Bridge. The work went to the joint venture of 3481 Condotte and 3869 Grandi Lavori Fincosit along with bridge design consultant Seteco Ingegneria as a subcontractor. Estimated cost is around €550 million for the 24m-wide single-support cable-stayed structure. The European Union will subsidise the work to around €15 million.

World Highways recently interviewed Niels Pedersen, head of bridges at the %$Linker: 2 External <?xml version="1.0" encoding="utf-16"?><dictionary /> 0 0 0 link-external Danish Road Directorate false https://www.worldhighways.com/categories/road-highway-structures/features/highly-relevant-denmarks-asset-management-for-bridges/ false false%>.

For more information on companies in this article

Related Content

  • Sleipner’s highlights system for moving excavators
    February 13, 2013
    Sleipner will explain the principle behind its “revolutionary method to improve the overall productivity in open-pit mines, quarries and construction sites.” The improvement is based on moving excavators around the site much faster than before, and additionally the Sleipner method saves time and money and considerably increases the excavators’ life, says the company.
  • Perkins will demonstrate how its engine will meet EU Stage IV/US Tier 4 Final emissions regulations
    January 6, 2017
    Perkins will showcase a complete line-up of Stage IV/Tier 4 Final engine solutions at Bauma, ahead of the new legislation next year. The four cylinder 854F-E34TA will demonstrate much of the technology on offer, as it uses Selective Catalytic Reduction (SCR) with an exhaust additive, plus a Diesel Oxidation Catalyst (DOC). Both Perkins’ 3.4 and 4.4-litre engine lines make do without a Diesel Particulate Filter (DPF), though the larger 7 litre will use a DPF as well.
  • Perkins will demonstrate how its engine will meet EU Stage IV/US Tier 4 Final emissions regulations
    February 7, 2013
    Perkins will showcase a complete line-up of Stage IV/Tier 4 Final engine solutions at Bauma, ahead of the new legislation next year. The four cylinder 854F-E34TA will demonstrate much of the technology on offer, as it uses Selective Catalytic Reduction (SCR) with an exhaust additive, plus a Diesel Oxidation Catalyst (DOC). Both Perkins’ 3.4 and 4.4-litre engine lines make do without a Diesel Particulate Filter (DPF), though the larger 7 litre will use a DPF as well.
  • New 40tonne ADT from Komatsu draws crowds at INTERMAT
    January 6, 2017
    The new HM400-3 articulated dump truck (ADT) from Komatsu can carry a full 40 tonnes and features a host of new technology in the drivetrain and in the cab. Its 353kW engine is fitted with a diesel particulate filter with computer-controlled regeneration so that no operator input is required. A computerised Transmission Control System replaces the need for limited slip differentials in the transmission as it activates the multi wet disc foundation brakes in any wheel that starts to spin. Furthermore, the s