A rough ride for Denmark’s National Road Directorate

Denmark’s National Audit Office has criticised the Danish National Road Directorate for consistently miscalculating the level of investment required for road projects. The Road Directorate – Vejdirektoratet - used 33% less than budgeted for road projects from 2007-2017. The audit office said that "budget calculations by the transport ministry, including the Road Directorate, have not been accurate enough". Jens Holmboe, head of the Road Directorate, rejected the criticism, saying that the Audit Office
November 1, 2019 Read time: 2 mins
Denmark is not spending enough? (Roskilde Bridge, photo courtesy RBAI joint venture)
Denmark’s 5285 National Audit Office has criticised the Danish National Road Directorate for consistently miscalculating the level of investment required for road projects.


The Road Directorate – Vejdirektoratet - used 33% less than budgeted for road projects from 2007-2017. The audit office said that "budget calculations by the transport ministry, including the Road Directorate, have not been accurate enough".

Jens Holmboe, head of the Road Directorate, rejected the criticism, saying that the Audit Office did not consider the effect the financial crisis had on building projects. The crisis resulted, among other things, in major price decreases for various road projects.

The Vejdirektoratet is responsible for the more than 1,200km of motorways, a number of main roads and many of the country's bridges – a total of about 4,000km. Denmark, being a country mainly of islands, relies on its bridges and tunnels to help unify the nation culturally. It also means that they are vastly more important to the economic well-being of the nation than in most other states.

In  mid-2015, Denmark became the first country in the world to rely on GPS probe data to monitor traffic and congestion on a national scale. It chose INRIX, a provider of transportation intelligence and connected car services, to set up a real-time traffic information system throughout the country. The directorate monitors traffic flow and gridlock across its entire national road network.

Early last year, an Italian joint venture won the construction contract for what will be one of Denmark’s longest bridges, the replacement 4km-long road and rail Storstrom Bridge. The work went to the joint venture of 3481 Condotte and 3869 Grandi Lavori Fincosit along with bridge design consultant Seteco Ingegneria as a subcontractor. Estimated cost is around €550 million for the 24m-wide single-support cable-stayed structure. The European Union will subsidise the work to around €15 million.

World Highways recently interviewed Niels Pedersen, head of bridges at the %$Linker: 2 External <?xml version="1.0" encoding="utf-16"?><dictionary /> 0 0 0 link-external Danish Road Directorate false https://www.worldhighways.com/categories/road-highway-structures/features/highly-relevant-denmarks-asset-management-for-bridges/ false false%>.

For more information on companies in this article

Related Content

  • Bigger and better INTERMAT show
    April 17, 2015
    INTERMAT is well-established as one of the biggest international shows for the construction equipment, machinery, technology and materials sector. This year INTERMAT and World of Concrete have pooled their expertise and reputations to launch World of Concrete Europe (WOC Europe). This collaboration will better meet the needs of the European concrete market by providing a comprehensive view of the sector.
  • Wacker Neuson launches DT08 Proline dumper
    January 6, 2017
    Part of Wacker Neuson’s new DT series of crawler-mounted dumpers, the DT08 Proline is said by the firm’s product manager Steffen Wiesener to have a more efficient hydraulic system than the standard DT08 model, improved operating and control comfort and a wider range of attachments. The DT08 is available in diesel or petrol versions.
  • Wacker Neuson launches DT08 Proline dumper
    March 9, 2012
    Part of Wacker Neuson’s new DT series of crawler-mounted dumpers, the DT08 Proline is said by the firm’s product manager Steffen Wiesener to have a more efficient hydraulic system than the standard DT08 model, improved operating and control comfort and a wider range of attachments. The DT08 is available in diesel or petrol versions.
  • Faster than a speeding cow – your local bus maybe?
    May 22, 2015
    A methane-powered bus has set a speed record for a regular city bus of nearly 124km/h at a test track in the UK, according to media reports. The bus, from the southern city of Reading, was converted to run on compressed methane from cow manure and was painted black and white like a Friesian cow. Mechanics removed the bus’s engine governor that restricted the vehicle’s speed to 90km/h. The bus then broke the record on the banked high-speed circuit at Millbrook Proving Ground, near the city of Bedford.