Poland bidders angry over Astaldi win for Warsaw Ring Road work

Four groups that made bids for building the southern section of the Warsaw Ring Road have filed complaints about how the national road authority GDDKiA chose Astaldi as the winner. Companies appealing to the National Board of Appeal (KIO) are Impresa Pizzarotti, Porr Polska, Salini Polska and IDS-BUD. The offer made by Italian company Astaldi was at least 25% less than the estimated €391 million cost of the project, according to Polish media reports. World Highways reported in February that Astaldi
June 18, 2015 Read time: 2 mins
Four groups that made bids for building the southern section of the Warsaw Ring Road have filed complaints about how the national road authority 1361 GDDKiA chose 1324 Astaldi as the winner.

Companies appealing to the National Board of Appeal (KIO) are Impresa Pizzarotti, 3976 Porr Polska, Salini Polska and IDS-BUD.

The offer made by Italian company Astaldi was at least 25% less than the estimated €391 million cost of the project, according to Polish media reports.

World Highways reported in February that Astaldi’s €290 million bid was the lowest offer for the project. The work calls for a 4.6km section of the route to be constructed, including what will be Poland’s longest road tunnel once complete.

The dispute comes just as an engineering and construction group led by Astaldi signed the largest construction financing package in Turkey’s history – US$5 billion - to refinance existing loans and provide new funding for a $6.4 billion toll road.

Astaldi and its Turkish partners 3338 Nurol Insaat, 3340 Makyol Insaat and Ozaltin Insaat agreed to the loan from nine lenders, including 3321 Deutsche Bank for the 400km road and suspension bridge across the Sea of Marmara. Financial news agency Bloomberg said the loan is the largest for a project in Turkey.

Astaldi said in a written statement that the new financial package will allow completion of the final portion of the 301km route linking the city of Bursa to the Aegean port of İzmir (Phase 2B) and to refinance the sections under construction for the Gebze-Orhangazi-Bursa link (Phase 1 and Phase 2A).

For more information on companies in this article

Related Content

  • Romanian highway works commencing
    July 15, 2022
    Highway works are commencing in Romania.
  • Mostostal Warszawa picked for S19 segment
    August 11, 2022
    The contract in northern Poland is worth around €211 million.
  • Opening St Petersburg's key tollway ring road
    May 15, 2012
    A new section of Western High Speed Diameter (WHSD) highway from the Ring Road (KAD) to the Hyundai plant in Kamenka, has been opened to traffic in St Petersburg. The WHSD and KAD interchange will be completed by 2012 when the entire third phase of the highway will be built. The US$7.23 billion WHSD Tollway in the city is sponsored by the Federal Road Agency and it is said to be one of the most important means of solving the city’s transport problems. It is a strategic investment project to develop the ci
  • Algerian highway dispute
    February 17, 2012
    Legal and technical complications are the cause of a dispute in between the Algerian transport authorities and four Japanese contractors over a US$6.56 billion highway project.