Poland bidders angry over Astaldi win for Warsaw Ring Road work

Four groups that made bids for building the southern section of the Warsaw Ring Road have filed complaints about how the national road authority GDDKiA chose Astaldi as the winner. Companies appealing to the National Board of Appeal (KIO) are Impresa Pizzarotti, Porr Polska, Salini Polska and IDS-BUD. The offer made by Italian company Astaldi was at least 25% less than the estimated €391 million cost of the project, according to Polish media reports. World Highways reported in February that Astaldi
June 18, 2015 Read time: 2 mins
Four groups that made bids for building the southern section of the Warsaw Ring Road have filed complaints about how the national road authority 1361 GDDKiA chose 1324 Astaldi as the winner.

Companies appealing to the National Board of Appeal (KIO) are Impresa Pizzarotti, 3976 Porr Polska, Salini Polska and IDS-BUD.

The offer made by Italian company Astaldi was at least 25% less than the estimated €391 million cost of the project, according to Polish media reports.

World Highways reported in February that Astaldi’s €290 million bid was the lowest offer for the project. The work calls for a 4.6km section of the route to be constructed, including what will be Poland’s longest road tunnel once complete.

The dispute comes just as an engineering and construction group led by Astaldi signed the largest construction financing package in Turkey’s history – US$5 billion - to refinance existing loans and provide new funding for a $6.4 billion toll road.

Astaldi and its Turkish partners 3338 Nurol Insaat, 3340 Makyol Insaat and Ozaltin Insaat agreed to the loan from nine lenders, including 3321 Deutsche Bank for the 400km road and suspension bridge across the Sea of Marmara. Financial news agency Bloomberg said the loan is the largest for a project in Turkey.

Astaldi said in a written statement that the new financial package will allow completion of the final portion of the 301km route linking the city of Bursa to the Aegean port of İzmir (Phase 2B) and to refinance the sections under construction for the Gebze-Orhangazi-Bursa link (Phase 1 and Phase 2A).

For more information on companies in this article

Related Content

  • Poland’s planned programme of highway construction
    December 13, 2013
    Poland’s National Road Construction Programme has been amended for the 2011-15 period. One of the new projects being handled is for the southern section of the ring-road (POW) for capital Warsaw will benefit. The tender process is opening for the construction of an 18.5km section of the S2 dual carriageway from Pulawska junction to Lubelska junction. The General Direction of National Roads and Motorways (GDDKiA) is keen for the southern Warsaw ring road to be open to traffic by 2019. The Pulawska-Lubleska s
  • Poland highway tender process opening
    January 3, 2017
    The tender process is opening in Poland for a stretch of highway connecting Napierki with Mlawa. This 14km stretch of the S7 dual carriageway is the first of four sections of the route to be offered for tender. The bidding process for the project is being managed by the Polish General Directorate for National Roads and Motorways (GDDKiA). Bids have to be received by the 21st February 2017, with 18 firms having been invited to tender for the work. The total value of the work to construct the four sections of
  • Turkish highways and bridge project financing secured
    June 7, 2018
    The financing package that will pay for Turkey’s €2.43 billion Malkara to Çanakkale highway and 1915 Çanakkale Bridge has now been secured. This follows on from Mott MacDonald completing its technical due diligence of the project documentation. The project will be handled under the PPP model. The centrepiece of the project is the €1.68 billion Çanakkale 1915 bridge. This will be over 4.6km long, with a 2,023m main span that will be the longest in the world for a suspension bridge. It will allow a clearance
  • VIDEO: Kolin-Kalyon and Limak-Cengiz win North Marmara connector tenders
    May 23, 2016
    Turkey has awarded the much-delayed tenders for the motorway connector roads to Istanbul’s Third Bosphorus Bridge.

    The 90km motorway section between Kinali and Odayeri was awarded to the Kolin-Kalyon joint-venture with completion in seven years and nine months, according to Turkish media reports. The 170km section between Kurtkoy and Akyazi was awarded to Limak-Cengiz joint-venture which will finish the work in six years and nine months.