Philippines to rethink Laguna Expressway highways work

The Philippines might separate a 47km six-lane road construction element from a complicated land reclamation and dike development contract recently shunned by preferred bidders. None of the three qualified bidders for the Laguna Lakeshore Expressway Dike public-private partnership deal submitted final bids for the contract. There were concerns over the legality of reclaiming 700 ha of land and whether investors could make money from it.
May 3, 2016 Read time: 2 mins

The Philippines might separate a 47km six-lane road construction element from a complicated land reclamation and dike development contract recently shunned by preferred bidders.

None of the three qualified bidders for the Laguna Lakeshore Expressway Dike public-private partnership deal submitted final bids for the contract. There were concerns over the legality of reclaiming 700 ha of land and whether investors could make money from it.

The pre-qualified consortia were Trident Infrastructure and Development consortium – consisting of SM Prime Holdings, Megaworld, Ayala Land and Aboitiz Equity Ventures - the Alloy-PAVI LLEDP Consortium and San Miguel Holdings

Work was to have included 700 ha of coastal reclamation of Laguna de Bay from Taguig in Metro Manila to Calamba and Los Baños in Laguna, as well as associated bridges, pumping stations and ancillary flood gates.

The expressway was to have coast around $860 million, according to some estimates. It was expected to reduce travel time between Metro Manila and Laguna from 90 minutes to 35 minutes, and ease traffic and mitigate flooding between Taguig and Los Baños.

Bidding had been delayed several times due to environmental concerns, including how the project might displace local fishing boats from their harbours and fishing grounds.

Leading the review of the unwanted contract is the Department of Public Works and Highways.

Business World On-Line quoted Andre Palacios, executive director of the Public-Private-Partnership Center, saying the government department is rethinking which components of the discredited contract might go together. There is a possibility that the road work is hived off.

Related Content

  • Philippines PPP project programme proposed
    April 10, 2014
    The Philippines Government is unveiling 15 key infrastructure projects worth a total of US$14 billion over the next 12 months. These will form part of the PPP project programme proposed by the Philippines Government. The projects include the $1.44 billion Laguna Lakeshore Expressway Dike project and the $313.16 million Motor Vehicle Inspection System. Meanwhile the Department of Public Works and Highways (DPWH) will be allocated a healthy $38.56 billion for road maintenance and repair activities by the gove
  • Philippines implementing transport projects
    March 3, 2017
    A series of major highway projects are now being implemented in the Philippines. Key projects being implemented close to Davao City include the US$380 million Davao City-Panabo City bypass, the $537.5 million Coastal Road and two flyovers worth $14 million in total. The bypass project will cut journey times and includes the construction of a tunnel section, with a portion of the funding being provided by the Japan International Cooperation Agency (JICA). The new coastal route will also cut congestion and jo
  • Philippines’s NEDA to consider two road PPP projects in November
    November 12, 2015
    The National Economic and Development Authority (NEDA) will consider approval of seven Public-Private Partnership (PPP) projects, two of them highways, by the end of this month. The highways are the US$516 million Manila connector road and the $209 million Plaridel toll road. A report by the Manila-based Business World Online newspaper said the deals are worth around US$3.65 billion.
  • Contract withdrawn for Philippines highway contract causing delay
    August 14, 2014
    The project to construct a connecting road between the South Luzon and North Luzon expressways in the Philippines now looks set to be delayed. The US$409 million contract previously awarded to a joint venture comprising Philippine National Construction Corp (PNCC) and Metro Pacific Investments Corp (MPIC), has been withdrawn for unspecified reasons. The country’s Department of Public Works and Highways says that the contract has been returned to the National Economic and Development Authority (NEDA) for new