Philippines to rethink Laguna Expressway highways work

The Philippines might separate a 47km six-lane road construction element from a complicated land reclamation and dike development contract recently shunned by preferred bidders. None of the three qualified bidders for the Laguna Lakeshore Expressway Dike public-private partnership deal submitted final bids for the contract. There were concerns over the legality of reclaiming 700 ha of land and whether investors could make money from it.
May 3, 2016 Read time: 2 mins

The Philippines might separate a 47km six-lane road construction element from a complicated land reclamation and dike development contract recently shunned by preferred bidders.

None of the three qualified bidders for the Laguna Lakeshore Expressway Dike public-private partnership deal submitted final bids for the contract. There were concerns over the legality of reclaiming 700 ha of land and whether investors could make money from it.

The pre-qualified consortia were Trident Infrastructure and Development consortium – consisting of SM Prime Holdings, Megaworld, Ayala Land and Aboitiz Equity Ventures - the Alloy-PAVI LLEDP Consortium and San Miguel Holdings

Work was to have included 700 ha of coastal reclamation of Laguna de Bay from Taguig in Metro Manila to Calamba and Los Baños in Laguna, as well as associated bridges, pumping stations and ancillary flood gates.

The expressway was to have coast around $860 million, according to some estimates. It was expected to reduce travel time between Metro Manila and Laguna from 90 minutes to 35 minutes, and ease traffic and mitigate flooding between Taguig and Los Baños.

Bidding had been delayed several times due to environmental concerns, including how the project might displace local fishing boats from their harbours and fishing grounds.

Leading the review of the unwanted contract is the Department of Public Works and Highways.

Business World On-Line quoted Andre Palacios, executive director of the Public-Private-Partnership Center, saying the government department is rethinking which components of the discredited contract might go together. There is a possibility that the road work is hived off.

Related Content

  • Reunion Island coastal road delays continue
    January 21, 2021
    Delays continue to trouble the Reunion Island coastal road project.
  • Cat paver helps ''safeguard Venice''
    July 23, 2012
    For centuries Venetians had given in to the Adriatic Sea, learning to celebrate its unique challenges rather than trying to hold back its tides, but that is changing. Built on an archipelago of 118 islands, with over 150 canals and over 400 bridges connecting the islands, visitors and residents to the old lagoon city travel only by water or on foot: it is considered Europe's largest car-free urban area. So the sight of a state-of-the-art Caterpillar AP655D asphalt paver is unusual, but it is assisting in a
  • Bidding is healthy for a contract for the I-77 Interstate highway in the US state of North Carolina with Spanish firms competing
    April 4, 2012
    Bidding is healthy for the I-77 Interstate highway project in the US state of North Carolina. This 47km highway runs from the city of Charlotte to Mooresville and the contract will be for a 50 year period. Spanish construction companies ACS, OHL and Ferrovial are all amongst the bidder for the US$501.5 million package, which includes construction, maintenance and. French firm Vinci has formed a partnership with US companies Parsons, Archer Western and Blythe Construction. ACS has ACS formed a consortium wit
  • Doha’s massive ring road expressway project
    July 10, 2019
    The huge Doha ring road project will help decongest the city and improve transport for Qatar