Philippines to rethink Laguna Expressway highways work

The Philippines might separate a 47km six-lane road construction element from a complicated land reclamation and dike development contract recently shunned by preferred bidders. None of the three qualified bidders for the Laguna Lakeshore Expressway Dike public-private partnership deal submitted final bids for the contract. There were concerns over the legality of reclaiming 700 ha of land and whether investors could make money from it.
May 3, 2016 Read time: 2 mins

The Philippines might separate a 47km six-lane road construction element from a complicated land reclamation and dike development contract recently shunned by preferred bidders.

None of the three qualified bidders for the Laguna Lakeshore Expressway Dike public-private partnership deal submitted final bids for the contract. There were concerns over the legality of reclaiming 700 ha of land and whether investors could make money from it.

The pre-qualified consortia were Trident Infrastructure and Development consortium – consisting of SM Prime Holdings, Megaworld, Ayala Land and Aboitiz Equity Ventures - the Alloy-PAVI LLEDP Consortium and San Miguel Holdings

Work was to have included 700 ha of coastal reclamation of Laguna de Bay from Taguig in Metro Manila to Calamba and Los Baños in Laguna, as well as associated bridges, pumping stations and ancillary flood gates.

The expressway was to have coast around $860 million, according to some estimates. It was expected to reduce travel time between Metro Manila and Laguna from 90 minutes to 35 minutes, and ease traffic and mitigate flooding between Taguig and Los Baños.

Bidding had been delayed several times due to environmental concerns, including how the project might displace local fishing boats from their harbours and fishing grounds.

Leading the review of the unwanted contract is the Department of Public Works and Highways.

Business World On-Line quoted Andre Palacios, executive director of the Public-Private-Partnership Center, saying the government department is rethinking which components of the discredited contract might go together. There is a possibility that the road work is hived off.

Related Content

  • Vietnam: North-South Expressway bidding
    November 17, 2022
    The package for the Can Tho-Hau Giang section has the biggest value, at US$320 million.
  • Philippines toll road deal reached
    October 15, 2019
    The first three stretches of the Cavite-Laguna Expressway in the Philippines should be open to traffic by the end of October 2019. Around 10,000 vehicles/day are expected to use the three stretches when they open. The 45km route is costing US$653.4 million to develop. When it is fully commissioned in the second quarter of 2022, will cut journey times between CAVITEx and SLEx to 45 minutes, compared with 150 minutes that it has taken to travel previously. MPCALA Holdings has the concession package for the ro
  • New highway project proposed for the Philippines
    September 15, 2017
    Plans have been drawn up in the Philippines for Cavite-Tagaytay-Batangas Expressway (CTBEx) project. The Metro Pacific Group submitted its proposals for the expressway to the Department of Public Works and Highways. The US$440.2 million expressway will improve the link from Cavite to Nasugbu and Tagaytay. The Metro Pacific Group hopes to receive the necessary approvals for the project by the end of 2017.
  • Indra wins tolling deal in Philippine capital Manila
    April 10, 2013
    Indra is supplying its sophisticated urban traffic control system to Metro Manila, the Philippines’ main metropolitan region. The Metro Manila area has more than 11 million residents and accounts for a significant proportion of the country’s entire traffic volume. This technology was selected as it involves proven systems and is already implemented in a number of cities in China, Brazil, Colombia and Spain. Indra is also involved with the toll system for the North Luzon Expressway (NLEX), one of the nation'