Mostostal Warszawa makes lowest bids in Poland’s S9 tenders

A Mostostal Warszawa consortium has reportedly made the lowest bids to build three sections of the S19 from Nisko to Sokolow Malopolski in south-eastern Poland. The consortium’s bid was just over €187 million in total. Other bids which were received from a Strabag consortium and a Budimex consortium.
November 24, 2017 Read time: 2 mins
A 3304 Mostostal Warszawa consortium has reportedly made the lowest bids to build three sections of the S19 from Nisko to Sokolow Malopolski in south-eastern Poland.


The consortium’s bid was just over €187 million in total. Other bids which were received from a 945 Strabag consortium and a 3302 Budimex consortium.

Poland’s roads authority 1361 GDDKiA is expected to sign a deal in the second quarter of 2018 with work to start after mid-2019 and completion in 2021.
 
Meanwhile, contractor 3544 Warbud has signed deal with the GDDLiA to build a 2.5km section of Warsaw ring-road for nearly €94 million. The section will be of three 3.5m-wide lanes and a hard shoulder in each direction. Delivery is expected by mid-April 2021.

In north-western Poland, an agreement has been signed for more than €117 million of European Union support for construction of a section of the S6 dual carriageway. Work includes building around 54km of road as well as a number of service stations and six junctions.

The north-western contract is divided into three sections: Goleniow-Nowogard, Nowogard-Ploty and Ploty-Kielpino. The first of the sections is scheduled for completion in April 2019 and the third in May 2019.

For more information on companies in this article

Related Content

  • Polish plans progressing
    October 3, 2014
    Plans are moving forward for a series of key highway projects in Poland. One project involves constructing three sections of the new southern ring road around Polish capital Warsaw. Building the 18.5km stretch that comprises the three sections is expected to cost in the region of €1.6 billion.
  • Poland: Budimex signs Olsytyn city ring-road contract
    April 4, 2016
    Budimex has signed a contract worth more than €214.3 million for construction of the second section of Olsztyn's ring-road. The section will be around 14.7km long and will be completed within 28 months. The bid by Budimex was the fourth lowest offer in the tender, as announced by the Polish General Directorate for National Roads and Motorways (GDDKiA).
  • Contractor STRABAG is building Poland’s S8 route
    February 9, 2016
    Austrian contractor STRABAG is now working on designing and building the new S8 route in Poland. This €57 million project will provide a new 10km route connecting Radziejowice and Przeszkoda. The road is being built from concrete and is due for completion within 31 months. The project was awarded to STRABAG by Poland’s General Directorate for National Roads and Highways (GDDKiA). In addition to building the dual carriageway, the work also involves constructing the Żabia Wola junction as well as several stru
  • Poland’s planned programme of highway construction
    December 13, 2013
    Poland’s National Road Construction Programme has been amended for the 2011-15 period. One of the new projects being handled is for the southern section of the ring-road (POW) for capital Warsaw will benefit. The tender process is opening for the construction of an 18.5km section of the S2 dual carriageway from Pulawska junction to Lubelska junction. The General Direction of National Roads and Motorways (GDDKiA) is keen for the southern Warsaw ring road to be open to traffic by 2019. The Pulawska-Lubleska s