Mombasa-Tanga link faces delays over design changes

Kenya has blamed design changes for delaying the start of work on a road linking the port of Mombasa to the Tansanian port of Tanga. The change to the key road’s design is from a single to dual carriageway along a section of the 445km transnational highway. However, the African Development Bank (AfDB), the principal financier of the project, said the Kenyan government itself was slow in completing preliminary studies, such as road designs, in order to start construction.
April 10, 2018 Read time: 3 mins
Kenya has blamed design changes for delaying the start of work on a road linking the port of Mombasa to the Tansanian port of Tanga.


The change to the key road’s design is from a single to dual carriageway along a section of the 445km transnational highway.

However, the 1586 African Development Bank (AfDB), the principal financier of the project, said the Kenyan government itself was slow in completing preliminary studies, such as road designs, in order to start construction.

The road from Malindi on the Kenyan coast to Bagamoyo - formerly a key trading port in north-eastern Tanzania during colonial times - will cost around US$751 million, according to the Kenya-based newspaper Business Daily Africa. AfDB will fund about 70% of the project, with the two countries covering 30% of the total cost in their respective territories.

Work on the mega project that is expected to take 36 months but the start of construction has been delayed since 2016. It was expected to start this year, but a start is now not likely until next year.

Kenya’s transport and infrastructure secretary James Macharia said the new designs will ensure that the stretch from Mtwapa to Nyali in Mombasa - including the Mtwapa Bridge - is expanded from a single to dual carriage as in the previous designs.

“We had to change the designs to make sure we do not have a bottleneck at Nyali-Mtwapa area because traffic there is a very big problem,” Macharia reportedly said. “Designs for the [Mtwapa] bridge can be complex and need time to ensure it is done properly.”

Kenya started the tendering process for contractors to do feasibility studies and environmental impact assessments last month; Tanzania has already completed this aspect of the project inside their borders.

“Tanzania is moving faster than Kenya, but since it is a multinational project, the two countries have to come together,” said Gabriel Negatu, the AfDB director-general for business development and delivery in East Africa. “Once the detailed designs are done, we will proceed either this year or next.”

The 250km Kenyan section of the transnational highway starts in Malindi and runs  through Mombasa and on to Lunga Lunga at the border with Tanzania. Most of the project is rehabilitation of the existing road.

It will then cross into Tanzania through Tanga port and stretch 175km to Bagamoyo, a world heritage town as designated by the United Nations Educational, Scientific and Cultural Organisation (1384 UNESCO).

This will be the third transnational road project by the two countries. Previous projects included the are the $260 million Arusha-Namanga-Athi River Road.

For more information on companies in this article

Related Content

  • Peru highway concessions face lengthy delays
    January 12, 2015
    Red tape and bureaucracy are to blame for delays to Peru’s highway concessions. Infrastructure association Afin cites these as the reasons the majority of Peru’s highway concessions have been held up, by as much as 10 years in certain instances. Business News Americas reports that so far, only 15% of Peru's 78,000km road network, around 12,445km, is paved according to Afin. The country has a particular need to revamp three major highways according to Afin: the 2,600km Pan- American highway, the 3,500km And
  • Questions and delays afflict some key Indonesian transport project
    March 28, 2014
    Indonesia’s transport expansion programme is seeing new projects commence, but others afflicted by questions over feasibility and delays. Questions over the economic feasibility of the proposed Sunda Strait Bridge project have been raised by the Public Works Ministry. This mega-project is intended to provide a road link between Sumatra and Java. But construction of the 30km structure could cost up to US$23 billion and might not be fully recovered, even if the investor collects toll fees under a 100-year con
  • AnyWay, De La Salle University to collaborate
    March 22, 2024
    Zeev Halber, Anyway chief executive, signed an agreement with the university’s Gokongwei College of Engineering to collaborate on research on climate resilient transportation infrastructure.
  • STRABAG wins Hungarian expressway contract
    December 20, 2017
    STRABAG has won the tendering process for a €125 million expressway construction contract in Hungary. The package of works is for the construction of the R76 expressway in western Hungary. The contract will involve building an 8.6km section of expressway along with a number of overbridges and will take 36 months to complete. The work is being carried out for the state-owned firm NIF Zrt. This will be the first section of the R76 expressway, running from Zalaegerszeg to the M7 motorway and the work will incl