Mombasa-Tanga link faces delays over design changes

Kenya has blamed design changes for delaying the start of work on a road linking the port of Mombasa to the Tansanian port of Tanga. The change to the key road’s design is from a single to dual carriageway along a section of the 445km transnational highway. However, the African Development Bank (AfDB), the principal financier of the project, said the Kenyan government itself was slow in completing preliminary studies, such as road designs, in order to start construction.
April 10, 2018 Read time: 3 mins
Kenya has blamed design changes for delaying the start of work on a road linking the port of Mombasa to the Tansanian port of Tanga.


The change to the key road’s design is from a single to dual carriageway along a section of the 445km transnational highway.

However, the 1586 African Development Bank (AfDB), the principal financier of the project, said the Kenyan government itself was slow in completing preliminary studies, such as road designs, in order to start construction.

The road from Malindi on the Kenyan coast to Bagamoyo - formerly a key trading port in north-eastern Tanzania during colonial times - will cost around US$751 million, according to the Kenya-based newspaper Business Daily Africa. AfDB will fund about 70% of the project, with the two countries covering 30% of the total cost in their respective territories.

Work on the mega project that is expected to take 36 months but the start of construction has been delayed since 2016. It was expected to start this year, but a start is now not likely until next year.

Kenya’s transport and infrastructure secretary James Macharia said the new designs will ensure that the stretch from Mtwapa to Nyali in Mombasa - including the Mtwapa Bridge - is expanded from a single to dual carriage as in the previous designs.

“We had to change the designs to make sure we do not have a bottleneck at Nyali-Mtwapa area because traffic there is a very big problem,” Macharia reportedly said. “Designs for the [Mtwapa] bridge can be complex and need time to ensure it is done properly.”

Kenya started the tendering process for contractors to do feasibility studies and environmental impact assessments last month; Tanzania has already completed this aspect of the project inside their borders.

“Tanzania is moving faster than Kenya, but since it is a multinational project, the two countries have to come together,” said Gabriel Negatu, the AfDB director-general for business development and delivery in East Africa. “Once the detailed designs are done, we will proceed either this year or next.”

The 250km Kenyan section of the transnational highway starts in Malindi and runs  through Mombasa and on to Lunga Lunga at the border with Tanzania. Most of the project is rehabilitation of the existing road.

It will then cross into Tanzania through Tanga port and stretch 175km to Bagamoyo, a world heritage town as designated by the United Nations Educational, Scientific and Cultural Organisation (1384 UNESCO).

This will be the third transnational road project by the two countries. Previous projects included the are the $260 million Arusha-Namanga-Athi River Road.

For more information on companies in this article

Related Content

  • DAFNI tests UK road infrastructure resilience
    June 10, 2019
    A new computer system is said to offer huge benefits for maintaining transport infrastructure. This is the product of a world-leading computing project and is called Data and Analytics Facility for National Infrastructure, DAFNI. The project commenced in 2017 to provide world-leading research capabilities to help improve the UK’s infrastructure systems, by making them more resilient and effective. DAFNI can help ensure the UK’s infrastructure is sustainable by running detailed simulations that show a range
  • Malaysia’s West Coast Expressway gets project finances in order
    July 2, 2015
    Malaysia’s West Coast Expressway company has reported that it will inject nearly US$425 million into its West Coast Expressway project. Total cost of the West Coast Expressway, which will stretch 233km between Banting in Selangor state and Taiping in Perak state on the Malaysian peninsula, is expected to be around $1.56 billion. The highway will be built over five years as a build-operate-transfer project with a concession of 50 years, The Star newspaper reported in February 2014.
  • China to set up “international courts” for Belt and Road disputes
    February 6, 2018
    China plans to set up an “international court” for settling disputes among companies participating in Belt and Road transportation infrastructure work, according to Chinese media. The Global Time newspaper – with strong links to the communist government – reported that Chinese companies are facing more foreign-related lawsuits as they step up investment and business in countries covered by Beijing’s Belt and Road Initiative. The report called Belt and Road “a brainchild of Xi”, referring to Xi Jinping
  • Poetry in motion
    August 9, 2018
    A heavy-lift operation by Roll-iT using Enerpac equipment delivered a bridge deck - with a poem engraved on the underside - to Antwerp’s old harbour Only when the deck of the new Londenbrug Bridge is raised do travellers see the poem by Antwerp poet Stijn Vranken. It is written large on the underside of the 300tonne prefabricated steel deck. People waiting for a ship to pass the raised bridge now contemplate the poem’s message about ships transporting goods and people to and from the four corners of the