Mombasa-Tanga link faces delays over design changes

Kenya has blamed design changes for delaying the start of work on a road linking the port of Mombasa to the Tansanian port of Tanga. The change to the key road’s design is from a single to dual carriageway along a section of the 445km transnational highway. However, the African Development Bank (AfDB), the principal financier of the project, said the Kenyan government itself was slow in completing preliminary studies, such as road designs, in order to start construction.
April 10, 2018 Read time: 3 mins
Kenya has blamed design changes for delaying the start of work on a road linking the port of Mombasa to the Tansanian port of Tanga.


The change to the key road’s design is from a single to dual carriageway along a section of the 445km transnational highway.

However, the 1586 African Development Bank (AfDB), the principal financier of the project, said the Kenyan government itself was slow in completing preliminary studies, such as road designs, in order to start construction.

The road from Malindi on the Kenyan coast to Bagamoyo - formerly a key trading port in north-eastern Tanzania during colonial times - will cost around US$751 million, according to the Kenya-based newspaper Business Daily Africa. AfDB will fund about 70% of the project, with the two countries covering 30% of the total cost in their respective territories.

Work on the mega project that is expected to take 36 months but the start of construction has been delayed since 2016. It was expected to start this year, but a start is now not likely until next year.

Kenya’s transport and infrastructure secretary James Macharia said the new designs will ensure that the stretch from Mtwapa to Nyali in Mombasa - including the Mtwapa Bridge - is expanded from a single to dual carriage as in the previous designs.

“We had to change the designs to make sure we do not have a bottleneck at Nyali-Mtwapa area because traffic there is a very big problem,” Macharia reportedly said. “Designs for the [Mtwapa] bridge can be complex and need time to ensure it is done properly.”

Kenya started the tendering process for contractors to do feasibility studies and environmental impact assessments last month; Tanzania has already completed this aspect of the project inside their borders.

“Tanzania is moving faster than Kenya, but since it is a multinational project, the two countries have to come together,” said Gabriel Negatu, the AfDB director-general for business development and delivery in East Africa. “Once the detailed designs are done, we will proceed either this year or next.”

The 250km Kenyan section of the transnational highway starts in Malindi and runs  through Mombasa and on to Lunga Lunga at the border with Tanzania. Most of the project is rehabilitation of the existing road.

It will then cross into Tanzania through Tanga port and stretch 175km to Bagamoyo, a world heritage town as designated by the United Nations Educational, Scientific and Cultural Organisation (1384 UNESCO).

This will be the third transnational road project by the two countries. Previous projects included the are the $260 million Arusha-Namanga-Athi River Road.

For more information on companies in this article

Related Content

  • CET opens new laboratory to service UK’s infrastructure projects
    October 23, 2017
    With over £300 billion of investment in infrastructure planned over the next four years in the UK, materials testing firm CET is gearing up to service a lot more projects – Kristina Smith visited the newest laboratory near Heathrow to find out more. The CET Group has ambitious plans. Over the next four years it wants to double the size of its business, which in the last year turned over £27 million. “There’s a lot of positivity out there,” said Gary Corrigan, managing director of the group’s infrastructu
  • A macro website launched for microsurfacing processes
    October 9, 2018
    RoadResource.org as a go-to website for surfacing information is now live When RoadResouce.org went live – quietly - in July it was the end of two years of hard work by three major US associations for pavement preservation. But there was no grand party or ceremonial pushing of the “go live” button, says Doug Hogue, vice president and general manager of VSS Macropaver. “For all of us in the industry July is a busy period that left little time to celebrate on the opening day,” says the 51-year-old chartere
  • KwaMhlanga Group buys Rapidmix concrete plant for South African roadwork
    May 14, 2018
    Rapid International of County Armagh, Northern Ireland, has supplied KwaMhlanga Group (Gauteng province, South Africa) with a new Rapidmix 400CW mobile continuous concrete mixing plant to produce road sub-base in South Africa. KwaMhlanga Group bought the Rapidmix plant for road rehabilitation via base layer stabilisation and road construction using sub-base layer stabilisation. The group’s previous production process resulted in inaccurate blending of emulsions and cement into aggregates and lower than des
  • Zimbabwe highway project linking with its neighbours
    November 28, 2016
    Zimbabwe’s Beitbridge to Chirundu highway link now looks set for a complete upgrade. The project has been planned for over 10 years but has faced a series of setbacks and delays, with funding having proved one of the biggest stumbling blocks in the past. The 897km highway runs from Beitbridge, located on the border with South Africa in the south of Zimbabwe all the way up to Chirundu, which is just over the border with Zambia in the north. The route includes part of the A4 highway in the south and the A1 hi