Mexico opens Escenica Alterna Tunnel in Acapulco

The first stage of the 3.3km Escenica Alterna Tunnel in Acapulco was opened this month. The three-lane tunnel – one is reversible – is costing around US$62 million and will improve connections between coastal areas and Diamante zone, as well as access to Acapulco International Airport. Gerardo Ruiz Esparza, Secretary of Communication and Transport, said that the project would be concluded in June with construction of Cayaco-Diamante elevated road. The project is funded by the National Infrastructure F
April 18, 2017 Read time: 1 min
The first stage of the 3.3km Escenica Alterna Tunnel in Acapulco was opened this month.

The three-lane tunnel – one is reversible – is costing around US$62 million and will improve connections between coastal areas and Diamante zone, as well as access to Acapulco International Airport.

Gerardo Ruiz Esparza, Secretary of Communication and Transport, said that the project would be concluded in June with construction of Cayaco-Diamante elevated road. The project is funded by the National Infrastructure Fund and money from main contractor IDEAL, part of Grupo Carso.

Related Content

  • Transstroy’s ambitions for Sochi 2014 Olympics and beyond
    September 30, 2013
    Igor Pankin is CEO of Transstroy, one of Russia’s largest transport infrastructure construction companies, a part of Oleg Deripaska’s Basic Element group. Created in 1992, the company has completed major construction projects with a combined worth of more than €4 billion (RUB 121 billion) The Olympic motto, ‘Swifter, Higher, Stronger’, is very appropriate for the Sochi 2014 Winter Olympics – and not just in reference to the action in its stadiums and on its slopes. The city has been transformed from a small
  • Colombia tunnel construction cost climbs
    January 25, 2018
    Work on the La Linea Tunnel project in Colombia has cost considerably more than first anticipated. The National Road Institute (Invias) says that the bill so far tops US$774 million. Extra costs of around $281.5 million have been incurred due to the need to drive a pilot tunnel as well as for three additional tunnel stretches as well as bridges along the approaches to the main tunnel. The project is now expected to be complete by the end of 2018, somewhat later than originally expected.
  • Norway’s long tunnel looks set to beat records
    September 19, 2016
    Norway looks set to retain its position as a leader in tunnelling with the project moving forward to build a new link connecting the city of Stavanger with Bokn. This 27km road tunnel is being designed to carry four lanes of traffic, which would make it the world’s longest underwater road tunnel. It will also be the world’s longest four lane tunnel as well as the world’s deepest road tunnel, dropping around 385-390m below sea level. The Rogaland Fixed Link will form part of the E39 route, connecting Kristia
  • Building Georgia’s transport connections to its neighbours
    October 26, 2016
    Georgia’s government aspires to turn the country into a regional transport-transit hub, and with renovated and expanded transportation infrastructure it knows that the country can offer significant opportunities to others in the region, and globally – Gordon Feller writes The Caucasus Transit Corridor (CTC) is the key transit-route between Western Europe and Central Asia for oil and gas, as well as dry cargo. CTC is part of TRACECA (TRAnsport Corridor Europe to Central Asia). This is the shortest route