Mexico: Acapulco’s Escenica Alterna tunnel to open in 2017

Construction of the Escenica Alterna tunnel in the Mexican resort port city of Acapulco is expected to be finished by June 2017. Work started on the 3.1km tunnel in 2013 with completion originally scheduled for October 2015. But financial problems delayed the US$200 million project which is now around three-quarters complete. Work by the contractor IDEAL - part of conglomerate Grupo Carso - includes construction of an elevated road connecting tunnel with Metlapil motorway.
June 6, 2016 Read time: 1 min
Construction of the Escenica Alterna tunnel in the Mexican resort port city of Acapulco is expected to be finished by June 2017.

Work started on the 3.1km tunnel in 2013 with completion originally scheduled for October 2015. But financial problems delayed the US$200 million project which is now around three-quarters complete.

Work by the contractor 3136 IDEAL - part of conglomerate Grupo Carso - includes construction of an elevated road connecting tunnel with Metlapil motorway.

For more information on companies in this article

Related Content

  • Russia's key highway development project
    May 28, 2012
    One of the largest construction programmes in Europe is being carried out to get a Russian resort ready for the Winter Olympics. Patrick Smith reports. Daytime temperatures top 30°C in September, and with hundreds of shops and hotels, it is not difficult to see why Sochi has become Russia's premier holiday playground. The city, on the east coast of the Black Sea, near the border with Georgia, bustles with tourists, and this is boosted with delegates at the 9th International Investment Forum Sochi 2010.
  • New Zealand’s Waterview project is moving closer to completion
    December 13, 2016
    New Zealand’s biggest road project is less than a year away from completion, and a lot of progress has been made since World Highways last looked at the project two years ago - Mary Searle Bell reports New Zealand’s Waterview project is moving closer to completion and will be the largest road project in the country. The NZ$2 billion Western Ring Route will see the creation of an alternative motorway to State Highway 1, which runs through the centre of Auckland. The 47km-long motorway will allow a large p
  • Colombia’s tunnel of woe faces further setback
    May 19, 2017
    The troubled tunnel construction project in Colombia to build the La Linea link has faced yet a further setback in its long tale of woe. The tender for the completion of the final 12% of the tunnel project has not managed to attract any interest from contractors. The budget for this work is an estimated US$77 million. A new tender process is being launched, with a submission deadline of 6th June 2017 and planned winner announcement on 4th July 2017. The contractor that had been building the tunnel failed to
  • Stuttgart’s Rosenstein Tunnel to open in March
    March 1, 2022
    Cost of the project, part of a larger interchange plan for the German city, is around €416 million.