Mexico: Acapulco’s Escenica Alterna tunnel to open in 2017

Construction of the Escenica Alterna tunnel in the Mexican resort port city of Acapulco is expected to be finished by June 2017. Work started on the 3.1km tunnel in 2013 with completion originally scheduled for October 2015. But financial problems delayed the US$200 million project which is now around three-quarters complete. Work by the contractor IDEAL - part of conglomerate Grupo Carso - includes construction of an elevated road connecting tunnel with Metlapil motorway.
June 6, 2016 Read time: 1 min
Construction of the Escenica Alterna tunnel in the Mexican resort port city of Acapulco is expected to be finished by June 2017.

Work started on the 3.1km tunnel in 2013 with completion originally scheduled for October 2015. But financial problems delayed the US$200 million project which is now around three-quarters complete.

Work by the contractor 3136 IDEAL - part of conglomerate Grupo Carso - includes construction of an elevated road connecting tunnel with Metlapil motorway.

For more information on companies in this article

Related Content

  • Auckland’s future strategic transport requirements
    July 5, 2012
    The Auckland Harbour Bridge is at the stage that it cannot cope with much more traffic, yet the population of the Auckland region continues to grow at a steady rate. Coupled with that, the bridge is a key link in the most important transport corridor in the country, State Highway One. Without it, the country would struggle to function. Not only home to New Zealand's largest city and one third of its population, Auckland's port is one of the country's largest. Some 140m north of the city is Marsden Point, th
  • Morocco’s new motorway links are boosting connectivity
    December 16, 2014
    Morocco’s massive motorway construction programme will improve transport connections and boost this North African country’s economy - Mike Woof reports A massive road building programme is transforming Morocco, with new motorways connecting cities and major towns, as well as many new rural roads being built. The Moroccan Government has set an impressive plan for its infrastructure investment that will see even the country’s small and remote villages having proper connections to the main road network. The
  • A decade for completing the 105km Cork-Limerick M20
    December 10, 2018
    It could be a decade before Ireland’s 105km Cork-Limerick M20 motorway is finished, the government has warned. Road safety groups and businesses have been pushing for the €900m M20 motorway because of issues over fatalities on the existing rural route. Simon Coveney, Ireland’s deputy prime minister, said the government was committed to the route – the largest motorway project to be undertaken in the next 25 years, and money has been earmarked for it. According to Irish media, Coveney also noted tha
  • Eastern European highway and tunnel projects
    May 15, 2012
    Serbia’s Corridor 10 project, seen as key to the country’s future economic development, is 20 years behind schedule. With construction delayed and the matter being debated, the Serbian Ministry for Infrastructure, which reported the schedule delay, says the country is working as fast as possible, with 22km being built/year. The corridor will connect the country with its neighbours and provide an important route for through traffic.