Mexico: Acapulco’s Escenica Alterna tunnel to open in 2017

Construction of the Escenica Alterna tunnel in the Mexican resort port city of Acapulco is expected to be finished by June 2017. Work started on the 3.1km tunnel in 2013 with completion originally scheduled for October 2015. But financial problems delayed the US$200 million project which is now around three-quarters complete. Work by the contractor IDEAL - part of conglomerate Grupo Carso - includes construction of an elevated road connecting tunnel with Metlapil motorway.
June 6, 2016 Read time: 1 min
Construction of the Escenica Alterna tunnel in the Mexican resort port city of Acapulco is expected to be finished by June 2017.

Work started on the 3.1km tunnel in 2013 with completion originally scheduled for October 2015. But financial problems delayed the US$200 million project which is now around three-quarters complete.

Work by the contractor 3136 IDEAL - part of conglomerate Grupo Carso - includes construction of an elevated road connecting tunnel with Metlapil motorway.

For more information on companies in this article

Related Content

  • Progress for planned Denmark-Germany immersed tunnel
    October 30, 2013
    A Danish company, Femern, is submitting documents for the Fehmarn Belt Fixed Link, an immersed tunnel that will connect Germany with Denmark. The project is expected to cost in the order of €5.5 billion to construct. An 18km immersed tunnel will link the islands of Fehmarn and Lolland. Fehmarn Island is already connected with Northern Germany’s mainland by a bridge, while Lolland is already connected by a tunnel and bridges with Zealand, a link that runs via the island of Falster
  • Proposed Slovakia tunnel project delayed
    October 4, 2016
    Delays seem likely for the project to build a tunnel link between Turany and Hubova in Slovakia. The 5.7km tunnel will form part of the D1 highway when complete but the construction schedule is being held back as the planned route runs through an aquifer area that provides water sources to three communities in the vicinity. A new route will have to be found so as to minimise the environmental impact. With the original timeline, construction of the tunnel could have commenced in 2017. But given the need to f
  • The tunnel connecting Denmark and Germany will now be delayed
    May 2, 2012
    The company handling the Fehmarnbelt tunnel project that will connect Denmark and Germany has confirmed that the project will now be delayed. Femern has now revealed that construction will not start before summer 2015, a year later than originally planned. Denmark is expected to commence its environmental compatibility study in May 2013.
  • Bratislava bypass and Karpaty tunnel completion set for 2030
    June 18, 2018
    Slovakia’s national motorway company NDS expects that the Bratislava bypass on the D4 motorway together with the Karpaty tunnel will be completed around 2030. The D4 motorway is part of the trans-European transport network and will connect with the planned R7 expressway linking western and eastern Slovakia, and the existing D1 and D2 motorways”. Apart from construction works on part of the D4 motorway, another two stretches are planned on this link, including the 3.6km stretch from Devinska Nova Ves t