Koridori Srbije said it is suffering delays to Corridor 10 work

Koridori Srbije, the contractor building the eastern section of the Corridor 10 motorway between Nis and the Bulgarian border, said completion will be delayed. The newspaper Vecernje Novosti reported that Koridori Srbije said works on the Prosek-Bancarevo section, Crvena Reka-Ciflik, Pirot East-Dimitrovgrad and the Bancarevo tunnel should be finished by the end of the year. Construction on the Dimitrovgrad ringroad are due to be completed in March.
October 18, 2016 Read time: 1 min
3235 Koridori Srbije, the contractor building the eastern section of the Corridor 10 motorway between Nis and the Bulgarian border, said completion will be delayed.

The newspaper Vecernje Novosti reported that Koridori Srbije said works on the Prosek-Bancarevo section, Crvena Reka-Ciflik, Pirot East-Dimitrovgrad and the Bancarevo tunnel should be finished by the end of the year.

Construction on the Dimitrovgrad ringroad are due to be completed in March.

For more information on companies in this article

Related Content

  • Breakthrough near for Čebrať Tunnel
    December 17, 2021
    The 3.5km-long tunnel through Slovakia’s Čebrať Hills is part of the D1 Ružomberok bypass.
  • EIB supporting Finnish PPP highway project
    June 17, 2015
    The European Investment Bank (EIB) is providing financial support for a key Finnish highway project, which will be run on a PPP basis. The EIB is providing a €102 million long-term loan to finance the construction of a 32km highway stretch between Hamina and Vaalimaa in Finland. This section will be built on a public-private-partnership (PPP) basis. Using this model is expected to reduce the construction cost and also shorten the time needed to complete the work in comparison to a conventional procurement p
  • Algeria signs off two contracts of Hauts Plateaux motorway work
    January 5, 2015
    The Algerian Council of Ministers has approved two contracts for stretches of road on the Hauts Plateaux motorway. No details of the contractors were given for the work that is to link Lambidiri to Draa Lahmar via Ouled Fadhel. Construction is expected to take 18 months. Last March, World Highways reported that work on the 1,000km Hauts-Plateaux motorway project was to begin that month. Construction cost for motorway’s 10 sections was estimated to be around US$8.94 billion, according to Algerian Minis
  • Major Europe-Asia bridge connection in Turkey
    July 1, 2014
    The 3rd Bosporus Bridge and the Northern Marmara Motorway will improve transport links between Europe and Asia and cut chronic congestion in Istanbul, Turkey’s largest city - Mike Woof reports Work is now well underway on the 3rd Bosporus Bridge and the Northern Marmara Motorway, providing a new link for Turkish city Istanbul and the region as a whole. This enormous bridge and highway project is breaking several records for Turkey in terms of scale, as well as setting a number of international records for e