Koridori Srbije said it is suffering delays to Corridor 10 work

Koridori Srbije, the contractor building the eastern section of the Corridor 10 motorway between Nis and the Bulgarian border, said completion will be delayed. The newspaper Vecernje Novosti reported that Koridori Srbije said works on the Prosek-Bancarevo section, Crvena Reka-Ciflik, Pirot East-Dimitrovgrad and the Bancarevo tunnel should be finished by the end of the year. Construction on the Dimitrovgrad ringroad are due to be completed in March.
October 18, 2016 Read time: 1 min
3235 Koridori Srbije, the contractor building the eastern section of the Corridor 10 motorway between Nis and the Bulgarian border, said completion will be delayed.

The newspaper Vecernje Novosti reported that Koridori Srbije said works on the Prosek-Bancarevo section, Crvena Reka-Ciflik, Pirot East-Dimitrovgrad and the Bancarevo tunnel should be finished by the end of the year.

Construction on the Dimitrovgrad ringroad are due to be completed in March.

For more information on companies in this article

Related Content

  • Serbia ponders penalties for Azvirt over Ljig-Preljina delays
    September 9, 2016
    The Serbian government has said it could issue penalties to the Azerbaijani construction company Azvirt for delays to work on the Ljig-Preljina Corridor 11 motorway project. Completion was set for the middle of next month. But last month the government said delays of around a month were due to problems construction the tunnel and bridge sections. The new route is expected to open around 40 days later than originally expected as a result.
  • Serbia and Bosnia consider options for a Belgrade-Sarajevo project
    December 19, 2016
    Serbia and Bosnia have started talks on constructing a fast highway between the Serbian capital Belgrade and Sarajevo, capital of Bosnia and Herzegovina. Serbian Vice President Zorana Mihajlovic met with the Bosnian minister of transport, Ismir Jusko, to agree on forming a joint working group to consider routes and road construction, according to the Serbian newspaper B92. Mihajlovic said that Serbia's main focus is for building the 100km Pozega-Visegrad section, of which 60km is in Serbia and 40km in
  • Two thirds of Corridor 10 motorway, Serbia finished
    July 3, 2013
    Serbian Minister of Transport Milutin Mrkonjic has reported that so far two thirds of construction works of the country’s Corridor 10 motorway have been completed. He said that a total of US$5.86 billion (€4.50bn) of loans have been approved for infrastructure projects, out of which $4.3 billion have not been realised, as previously stated by the Minister of Finance, Mladan Dinkic. The minister said that the Corridor 10’s most difficult build sections were between Nis and Dimitrovgrad, which has three large
  • Serbia says Corridor 10 completion to be delayed
    June 12, 2017
    Delays will hit Serbia’s Corridor 10 motorway project that was due for completion later this year. Serbia’s Minister of Construction, Zorana Mihajlovic, said that her department will soon publish as report on the delays, suggesting options for speeding up the work.