Key Colombia tunnel projects delayed

Construction work on Colombia’s two key tunnel projects is being delayed, with insufficient funding proving a major challenge. Both the Toyo Tunnel and La Linea Tunnel projects are behind schedule. In addition, the project to construct the Pumajero Bridge is also being delayed due to a lack of funds.Part of the problems is that the designs for these projects have been revised as construction work has progressed. However the additional funds to pay for the new design features added have not been fully
September 21, 2018 Read time: 2 mins

Construction work on Colombia’s two key tunnel projects is being delayed, with insufficient funding proving a major challenge. Both the Toyo Tunnel and La Linea Tunnel projects are behind schedule. In addition, the project to construct the Pumajero Bridge is also being delayed due to a lack of funds.

Part of the problems is that the designs for these projects have been revised as construction work has progressed. However the additional funds to pay for the new design features added have not been fully released. This is a particularly problem with the La Linea Tunnel project, which has been revised a number of times. Civil works on the tunnel should now be finished in October 2019 with the route expected to open for traffic in May 2020, but various link roads, bridges and interchanges as well as the tunnel’s traffic control and ventilation systems still have to be completed.

Meanwhile there are also concerns over the condition of much of Colombia’s road network. The country’s Association of Freight Transporters (Colfecar) claims that 43.6% of Colombia’s surfaced roads require maintenance and show signs of heavy wear. According to Colfecar, just 9.5% of Colombia’s surfaced roads are in good condition, which is having a detrimental effect on transport costs.

Related Content

  • Costa Rica road projects moving forward - slowly
    July 18, 2017
    Costa Rica is moving ahead with a series of major road projects, but progress is proving slower than anticipated or desired. The Costa Rica Government is struggling to achieve satisfactory progress with its overall road improvement programme. So far the key focus has been on maintaining existing links rather than building and improving road connections. The country’s National Laboratory for Structural Material and Models (Lanamme) has produced a report revealing that 85% of the national roads are in accepta
  • Colombia’s Toyo Tunnel project in hand
    May 31, 2019
    Progress is being made for Colombia’s Toyo Tunnel project. Around 20% of the work has been carried out. Building the tunnel and the first stage of the connecting highway sections in Antioquia includes the construction of 17 bridges, seven tunnel sections and 4.4km of road. Tendering for the second stage of the project is due to start soon and will include building a further 19.4km of highway. The Toyo Tunnel project and the entire highway was originally expected to cost US$603.5 million but is now expected
  • Key highway project in Colombia faces delay
    December 2, 2013
    Work on a key stretch of Colombia’s Ruta del Sol highway project is behind schedule, with the route now unlikely to open to traffic before 2017. The 21.6km section of the highway facing these delays will link Villeta and Guaduas in Cundinamarca. A key challenge is technical as the US engineering firm Gall Zeidler Consultants has warned Colombia’s infrastructure agency (ANI) that this section of the route is geologically unstable. The proposed route could be at risk from slippage and will need to be stabilis
  • Tampere road tunnel - a strategic link for central Finland
    April 4, 2016
    Progress has been good for an important underground road link in Finland reports Adrian Greeman. Assuming all goes well, the new Ranta, or Lakeside, tunnel in Tampere will open in full six months early; traffic could be running by the end of this year. Work on transforming the rundown city centre with new developments will get a major boost. It is a major achievement on a four-year-long project bringing significant benefits to one of Finland's largest cities. From the government's point of view the scheme w