Key Colombia tunnel projects delayed

Construction work on Colombia’s two key tunnel projects is being delayed, with insufficient funding proving a major challenge. Both the Toyo Tunnel and La Linea Tunnel projects are behind schedule. In addition, the project to construct the Pumajero Bridge is also being delayed due to a lack of funds.Part of the problems is that the designs for these projects have been revised as construction work has progressed. However the additional funds to pay for the new design features added have not been fully
September 21, 2018 Read time: 2 mins

Construction work on Colombia’s two key tunnel projects is being delayed, with insufficient funding proving a major challenge. Both the Toyo Tunnel and La Linea Tunnel projects are behind schedule. In addition, the project to construct the Pumajero Bridge is also being delayed due to a lack of funds.

Part of the problems is that the designs for these projects have been revised as construction work has progressed. However the additional funds to pay for the new design features added have not been fully released. This is a particularly problem with the La Linea Tunnel project, which has been revised a number of times. Civil works on the tunnel should now be finished in October 2019 with the route expected to open for traffic in May 2020, but various link roads, bridges and interchanges as well as the tunnel’s traffic control and ventilation systems still have to be completed.

Meanwhile there are also concerns over the condition of much of Colombia’s road network. The country’s Association of Freight Transporters (Colfecar) claims that 43.6% of Colombia’s surfaced roads require maintenance and show signs of heavy wear. According to Colfecar, just 9.5% of Colombia’s surfaced roads are in good condition, which is having a detrimental effect on transport costs.

Related Content

  • Russia’s most expensive road project to commence
    January 15, 2019
    Construction work is being planned for Russia’s most expensive road, which will be built in south of the country – Eugene Gerden reports Work is due to commence shortly on Russia’s most expensive road, in the south of the country. The highway will form part of the existing 1,600km Moscow-Sochi road, according to recent statements from senior officials at the Russian Ministry of Transport as well as local analysts. As part of the project, the Russian Government, together with private investors, plans to
  • Colombia’s Toyo Tunnel project underway
    September 14, 2018
    Construction is ongoing for Colombia’s Toyo tunnel project in Antioquia. The tunnel is located between Giraldo and Canasgordas and some 120km from Medellin. The tunnel should open to traffic in 2024 if the project sticks to its planned schedule. The main tunnel section will measure some 9.85km-long although the project involves drilling side tunnels and emergency areas. The work is costing US$588.4 million.
  • Tunnel project of Chilean capital Santiago
    April 8, 2015
    Tunnel construction in Chilean capital Santiago will help cut chronic congestion – Mauro Nogarin & Mike Woof write. Chile’s capital Santiago is a thriving city having benefited from the country’s economy growing strongly in recent years. The massive copper mining sector has helped boost the country’s GDP significantly in the past few decades, also aided by the growing international reputation of Chile’s large wine industry. The steady economic growth has resulted in an equally steady growth in average incom
  • A new highway for northern Colombia
    July 17, 2023
    The Pamplona-Cúcuta highway is playing an important role for the development of northern Colombia