JP Autoceste eyes 2020 as completion date for Bosnia’s Corridor 5c

Around two-thirds of the Corridor 5c motorway project is expected to be completed by 2020, according to the director of the Bosnian motorways company JP Autoceste. Jasmin Buco said that 120km out of 337km of the motorway are complete. The corridor section, to connect Budapest with Ploce port in Croatia, is taking the most time. He said that the cost of the remaining part of the motorway is expected to be around €2.81 billion.
March 3, 2016 Read time: 2 mins
Around two-thirds of the Corridor 5c motorway project is expected to be completed by 2020, according to the director of the Bosnian motorways company JP Autoceste.

Jasmin Buco said that 120km out of 337km of the motorway are complete.

The corridor section, to connect Budapest with Ploce port in Croatia, is taking the most time.

He said that the cost of the remaining part of the motorway is expected to be around €2.81 billion.

Buco said he expects that among new projects to start this year will be the Pocitelj-Zvirovici and Buna-POcitelj roads, worth around €130 million, and the two parts of the Zenicka ringroad.

Corridor Vc, or 5c, is designed to connect Kiev in the Ukraine to Slovakia and Hungary and run through Bosnia to Croatia’s Adriatic coast. The pan-European corridor consists of three branches, of which Vc follows a route from Budapest in Hungary to Ploce on the Croatian coast.

The longest stretch of Vc lies in Bosnia and Herzegovina, covering 337km.

In mid-2014, a 6km stretch of the highway between Sarajevo and Zenica was opened that included a 3km-loong tunnel. The March 1 tunnel, named after date of Bosnia's independence referendum, meant that the journey between the two cities was cut from one hour to 30 minutes.

The tunnel cost around €62 million had been under construction for several years, first by two Slovenian companies that eventually which went bankrupt, and later by a consortium of Bosnian companies, according to a report by Balkan Insight at the time. The tunnel is the longest in Bosnia and is one of the most important infrastructure projects to be completed since the 1992-5 war

Related Content

  • Ring road for Sarajevo nears completion
    December 17, 2012
    The Sarajevo Ring Road in Bosnia and Herzegovina is expected to be completed by October 2012. The construction of the 5.6km long highway from Josanica to Butila is being carried out by a consortium of companies made up of HP Investing and Strabag. The completed Ring Road will be part of the future Corridor Vc motorway. Bosnia and Herzegovina Federal Minister of Transport and Telecoms, Enver Bijedic, and State Minister of Telecoms and Transport and Director of the roads company JP Ceste FBiH, Filip Vujevo, r
  • Bosnia road tunnel under construction
    August 12, 2021
    A key road tunnel link is under construction in Bosnia.
  • Date set to complete D1 Višňové Tunnel section
    July 20, 2023
    The D1 section between Lietavská Lúčka and Dubná Skala in Slovakia includes the partially completed 7.5km twin-tube Višňové Tunnel - to be the country's longest.
  • Tender evaluation nears for Croatia’s Peljeski Bridge Project
    September 22, 2017
    Croatia’s roads agency Hrvatske Ceste will soon start evaluating tenders for the controversial Peljeski Bridge project, according to national media. Bids for construction of the four-lane 2.4km long bridge have been submitted by the China Road and Bridge Corporation, Austria's Strabag as well as consortia headed by Italy’s Astaldi and the Turkish company Ictas. The bridge will connect Croatian territory by traversing the Adriatic Sea’s Mali Ston Bay.