Indonesia’s road revamp is seeing new road transport connections

Indonesia’s road development programme is continuing, with a series of major projects being carried out across the country that will boost transport connections. State funding will help progress on the Trans-Sumatra toll road, paying for six sections of the road link. In all the 1,480km toll road project is expected to cost nearly US$11.85 billion, with state funding paying for a significant portion of the work So far the state-owned construction firm, Hutama Karya, which is building much of the route has
July 16, 2018 Read time: 2 mins
Indonesia’s road development programme is continuing, with a series of major projects being carried out across the country that will boost transport connections.


State funding will help progress on the Trans-Sumatra toll road, paying for six sections of the road link. In all the 1,480km toll road project is expected to cost nearly US$11.85 billion, with state funding paying for a significant portion of the work So far the state-owned construction firm, 5206 Hutama Karya, which is building much of the route has received state funding for the project worth $250.9 million. However Hutama Karywa is calling for $871.2 million of state funding for the project.

Tendering is commencing for inner-city toll roads in Indonesia’s capital, Jakarata. In all the six toll road sections will measure nearly 70km long, with a total expected pricetag of around $2.87 billion. The project is being handled by Jakarta Toll Development Jaya Pratama (JTD), with the works planned to be carried out under design and build contracts.

And a feasibility study for a new road link to Merak Port on the northern tip of Indonesia’s island of Java suggests that the project will not be practical, without state assistance on top of the expected private investment. Buying the land and building the 5.5km access road is expected to cost $125.45 million. To make the projects feasible would require boosting traffic in and out of the port to around 40,000 vehicles/day, which could be achieved by developing the port’s ship traffic. At present only 12,0000-16,000 vehicles/day enter or leave the port area.

For more information on companies in this article

Related Content

  • New tolled highway plans for Indonesia
    November 1, 2012
    The authorities in Indonesia have set out extensive plans to source funding for new tolled highways. In all seven highway projects have been identified as crucial to expanding the network and improving connectivity for the Indonesian islands of Sulawesi, Java and Sumatra. Some US$25 billion in loans from overseas has been sourced by the Public Works Ministry of Indonesia.
  • Waskita Karya seeks loan for Pejagan-Pemalang toll road on Java
    January 12, 2015
    Indonesian state-owned construction firm Waskita Karya will seek a bank loan of US$338 million for its work on the Pejagan-Pemalang toll project in central Java island. The project is being managed by Pejagan Pemalang Toll Road, a subsidiary of Waskita Karya. Waskita company secretary Antonius Yulianto Nugroho said the firm has enough cash resources to cover a quarter of its financial commitment on the project and is targeting bank loans to cover the other 75%. Waskita Karya plans to carry out a bond
  • Sections nearly ready for Indonesia’s trans-Sumatra route
    March 19, 2019
    Key sections of Indonesia’s important trans-Sumatra highway project are nearly ready for traffic. A 350km stretch that will connect with the city of Palembang should be open shortly. Meanwhile construction of the 141km Bakauheni to Terbanggi Bedar stretch is now starting, with this work being carried out by contractor Hutama Karya. The plans for the 2,765km trans-Sumatra toll road project call for the route to be complete by 2024. This will connect Aceh at the northern end of Sumatra with Lampung on the so
  • New toll roads panned for Indonesia
    December 16, 2014
    Two major new toll road projects are now in planning for Indonesia. One is for the Palembang-Indralaya toll project while the other is for the Soreang-Pasir Koja toll road. The South Sumatra provincial government believes that the Palembang-Indralaya toll road project will cost US$319.2 million, and feature a pay-back period of 18 years and 11 months. The investors in the project include the construction firms, Jasa Marga and Hutama Karya as well as the provincial government-owned Prodexim. Hutama Karya is