Gordie Howe Bridge on schedule for 2024

Slowdowns over COVID but time to regain momentum, says WDBA.
By David Arminas June 19, 2020 Read time: 2 mins
Construction off footings on the Canadian side has progressed (photo courtesy WDBA)

Despite slower progress than hoped for due to COVID protection measures, completion for the Gordie Howe International Bridge is on schedule for late 2024.

Safety measures for workers include daily screening for virus symptoms, the wearing of face masks and physical distancing, said Bryce Phillips, chief executive of the Windsor-Detroit Bridge Authority.

“It’s been almost three months dealing with COVID-19 and we are working to understand the impacts and how can we mitigate those impacts,” said Phillips during an on-line update of progress this month. “The reason why we are still showing the end of 2024 [as completion] is because that is four years away and there is still a lot of opportunity…to mitigate against what’s happened with COVID-19.”

Phillips, however, acknowledged that challenges remain for continuing to work simultaneously on the project’s four components – the bridge, the Canadian and US ports of entry and the bridge’s Michigan Interchange.

The 2.5km-long six-lane bridge will have a cycle and pedestrian path.

Final design of the bridge is being reviewed by international experts, said Aaron Epstein, chief executive of Bridging North America, the consortium that won the $5.7 billion fixed-priced public-private partnership deal in 2018. It includes design-build, operation, maintenance and rehabilitation.

BNA include ACS Infrastructure Canada, Dragados Canada, Fluor Canada, Aecon, Aecom, RBC Dominion Securities, Carlos Fernandez Casado and FHECOR Ingenieros Consultores, Moriyama & Teshima and Smith-Miller+Hawkinson Architects.

Ongoing work includes the placing of around 150,000 wick drains. Bridge footing are finished and tower footings are under construction and “will be seen above ground later this year”, said Epstein.

A 4km perimeter access road around the Canadian port of entry is ready and hydro transmission lines are undergoing testing.

The Windsor-Detroit Bridge Authority is a not-for-profit Canadian corporation created to deliver the Gordie Howe Bridge through a public-private partnership. WDBA is responsible for overseeing and managing the construction and operation of the crossing.

Michigan state’s department of transportation is working with WDBA on the US components of the bridge project.

The bridge is named after Canadian professional ice hockey player Gordie Howe, who spent years playing for the US team Detroit Red Wings of the National Hockey League.

For more information on companies in this article

Related Content

  • Montreal’s new Champlain Bridge is shaping up for Christmas
    September 10, 2018
    Montreal’s Champlain Bridges - one going up, one coming down, reports David Arminas The importance of the new Champlain Bridge to Montreal and Canada can’t be overstated, given the crumbling nature of the not-so-old original Champlain Bridge. The original steel truss affair across the St Lawrence River and the adjacent St Lawrence Seaway canal is “a lifeline for residents and businesses” in greater Montréal, according to the national Auditor General - the public sector spending watchdog. “It accommodates
  • Quebec to build new Mercier Bridge for Montreal city
    May 12, 2017
    The Canadian province of Quebec plans to build a US$219 million bridge across the St Lawrence River alongside the existing Mercier Bridge in the city of Montreal. Provincial government cabinet ministers Pierre Moreau and Geoff Kelley confirmed that a new bridge is forthcoming, but gave schedule for procurement or construction start, according to local media. However, Moreau said the work will begin probably before the new Champlain Bridge is finished at the start of 2019. Construction of the new Champlain B
  • Temporary bridges for Michigan highway works
    September 21, 2023
    Temporary bridges will help with Michigan highway works.
  • ARTBA’s research reveals US public supports infrastructure investment
    November 15, 2012
    According to the American Road & Transportation Builders Association (ARTBA), US voters are keen to see increased spending on infrastructure. ARTBA’s analysis suggests that voters approve nearly 70% of state and local transportation ballot initiatives, which is consistent with the results of the last four US elections. ARTBA tracked 31 measures overall; five were statewide initiatives and 26 were local. The measures would increase or extend funding for highways, bridges and transit. All of the seven bond in