Ferry operators sink the financing plan for Fehmarn Belt link

The Court of Justice of the European Union has said Denmark’s state grant aid to the proposed Fehmarn Belt link is illegal under EU rules. The court noted that the European Commission approved the Fehmarn project’s financing – total cost likely around the €8.7 billion - in July 2015 without a formal procedure. Denmark is completely responsible for financing the project that will replace a ferry service. Part of the funds were to come through the European Union and its Connecting Europe Facility for tr
December 17, 2018 Read time: 3 mins
Fehmarn Belt financing: up in the air for undersea tunnel

The Court of Justice of the European Union has said Denmark’s state grant aid to the proposed Fehmarn Belt link is illegal under EU rules.

The court noted that the European Commission approved the Fehmarn project’s financing – total cost likely around the €8.7 billion - in July 2015 without a formal procedure.

Denmark is completely responsible for financing the project that will replace a ferry service. Part of the funds were to come through the European Union and its Connecting Europe Facility for transportation.

Ferry operators Scandlines and Stena Line which provide services between Europe and the Scandinavian peninsula, argued in the European Court that the grant level to be given to whichever company operating the toll structure is based on unrealistically high traffic volume predictions.

The Fehmarn Belt is a strait between the German island of Fehmarn and the Danish island of Lolland. Ferries connects the islands in the region. Completion of the €8.7 billion project has been set for 2028. However, even before the European Court ruling, the project’s approval process had been bogged down over environmental issues, especially within the German state of Schleswig-Holstein in which the southern end of 18km immersed tunnel will surface.

“We are satisfied with the ruling of the Court of Justice of the European Union. (…) Scandlines is not against a Fehmarn connection established with state aid. State aid may be necessary when completing such large-scale projects,” said Søren Poulsgaard Jensen, chief executive of Scandlines.

“However, we do expect correct procedure, which entails transparency and fair competition. The aid must therefore be accurately and realistically defined, and it must be based on consistent assumptions and safeguarded against abuse. It is decisive for us that the tunnel cannot use the state finances as its sees fit to impose taxpayer-financed price pressure when traffic volumes do not live up to the optimistic prognoses and the ferries appear competitive.”
 
The arguments are in line with Stena Line’s appeal which questioned the necessity of the aid, the duration of the aid and the undue distortion to the market by allowing the Fehmarn fixed link to dramatically reduce prices.

“In this case State aid has been granted illegally. That’s why we welcome the decision from the court to annul the aid granted by the Commission for the construction of the Fehmarn Belt connection,” said Claes Berglund, director public affairs and sustainability for Stena.

A Rambøll-Arup-TEC consultancy joint venture is engaged in a client consultancy services contract with 4782 Femern. The joint venture has also worked on other landmark infrastructure projects, including the Øresund Tunnel in Denmark, the City Tunnel in Malmö, Sweden, the Medway Tunnel in England, as well as underground rail systems in Amsterdam and Copenhagen.

8721 COWI is carrying out the detailed design of the tunnel (north tunnel section, south tunnel section, and ramps & portals). Meanwhile, 3392 SWECO is handling the design for the dredging and reclamation work.
 
A second framework contract, for technical support services to Femern, is being carried out by ÅF-Hansen & Henneberg.

For more information on companies in this article

Related Content

  • Nynas reorganisation complete
    December 9, 2020
    Nynas has completed its reorganisation work.
  • Montenegro spends €198m on upgrades in past five years
    November 2, 2018
    Montenegro has spent €198 million on road maintenance and construction in the past five years, according to Mirsad Ibrahimovic, director of the Directorate for State Roads. The government also announced this past summer that construction of the Bar-Bolijare highway is being accelerated. China Roads and Bridges Company is the main contractor the Podgoric-to-Matesevo stretch, with work set to remain within the €194 million budget.
  • Lagos state lights up with Low Energy Designs
    March 9, 2018
    Nigeria’s Lagos state government has outsourced around a third of its street lighting under a deal with UK manufacturer Low Energy Designs. A total of 10,000 LED Street lights are set to be installed in Lagos, Nigeria by a United Kingdom firm, Low Energy Designs. The Lagos State Government recently entered into a partnership with the UK Company. The partnership deal will see LED replace up to 10,000 lights over 300km of state roads within the next year at a cost of US$7 million, Nigeria’s media reported.
  • Danish days for a Hitachi ZW220-6 wheel loader
    February 6, 2018
    A new Hitachi ZW220-6 wheeled loader has been delivered to Jysk Kloak Entreprise, a sewage and landscaping contractor in Tjæreborg on the coast of Denmark. It is the latest addition to the company’s Hitachi fleet, which includes a ZX250LC-6 medium and three mini excavators , the ZX10U-2, ZX18-3 and ZX27-3. “We needed the most versatile model available for our requirements,” said company owner Jan Christensen. Fitted with additional lights and a larger 4m³ bucket, the wheeled loader was supplied in Februa