Fehmarnbelt Tunnel start looms on the horizon - 2020

Work on the €7 billion immersed tunnel under the Fehmarnbelt could begin in 2020, according to the Danish state planning and operating company Femern. A construction start has been delayed on the 18km tunnel that will run between Germany and Denmark because of environmental and consultation issues in Germany. But Claus Baunkjaer, chief executive of Femern, said he is confident that Germany will give approval next year with another two years of preparations. Baunkjaer noted that Denmark is all set to p
October 20, 2017 Read time: 3 mins
Fehmarnbelt Tunnel: a start is in sight, according to Claus Baunkjaer, head of Femern
Work on the €7 billion immersed tunnel under the Fehmarnbelt could begin in 2020, according to the Danish state planning and operating company 4782 Femern.


A construction start has been delayed on the 18km tunnel that will run between Germany and Denmark because of environmental and consultation issues in Germany. But Claus Baunkjaer, chief executive of Femern, said he is confident that Germany will give approval next year with another two years of preparations.

Baunkjaer noted that Denmark is all set to proceed with its part of the work. The finances have been secured and the construction firm has been chosen.

The Fehmarn Belt is a strait between the German island of Fehmarn and the Danish island of Lolland. Currently, a ferry connects the two islands. Final planning approval is expected in 2018 with project completion by 2028. But the approval process has been bogged down over environmental issues being considered by the German state of Schleswig-Holstein in which the southern end of 18km immersed tunnel will surface.

On top of the €7 billion construction cost for the tunnel, financing for another €1 billion is in place should it be needed for unexpected problems and delays. Denmark is completely responsible for financing the project that will replace a ferry service.

Earlier this year, a report commissioned by German ferry operator Scandilines suggested that the Fehmarn tunnel will never be economically viable. Revenue and traffic forecasts are unrealistically high, noted the report completed by German consultancy DIW Econ. It is unlikely that the latest cost to build the massive road tunnel, around €7.4 billion, would ever be recovered.

DIW Econ’s 13-page report is based around mathematical calculations of a price war between the ferry and tunnel operators. Tunnel operator Fixed Link has said it will charge around €65 per car and €267 for a truck. The report suggests that the ferry operator will undercut the tunnel operator by half, and take 37% of the car market and retain at least 80% of the truck market.

“This will secure the ferry a decent profit, so that the ferry will stay in the market,” notes the authors. “The report finds that in the baseline scenario the tunnel incurs a loss of at least €3 billion over the 50 years [concession] due to the large market shares captured by the ferry.”

The report says that Fixed Link will make a profit only if the ferry services ceases operations. However, there are variables, acknowledge the authors, and the calculations and results could change with time.

Femern dismissed the claims. The project's financial situation is secure according to financial analysis of the project by international auditors on behalf of the Danish Ministry of Transport. Femern also said that the project will be paid off over 36 years, as noted in the original plans.

For more information on companies in this article

Related Content

  • Road user charging comes to the UK?
    December 14, 2017
    A new funding scheme for England’s proposed Major Road Network was greeted with enthusiasm by local authorities which partly pay for road upkeep. But this enthusiasm may be premature, explains Alan Pauling*
  • Consultation soon for Vancouver area’s Massey Tunnel replacement
    September 19, 2019
    The Canadian province of British Columbia could put options for a Massey Tunnel replacement out to consultation late this year or early next. A statement from the BC ministry of transportation and infrastructure said the government is in discussions with various stakeholders about which options it will put out for consultation. Whatever option is chosen to replace the ageing four-lane Massey Tunnel – be it a bridge or another tunnel – it will be will be either six or eight lanes, according to the gove
  • EU construction machinery sector needs resolve as Brexit looms
    February 14, 2019
    German construction machinery manufacturers are concerned about a no-deal Brexit – UK exiting the European Union - and the possible disintegration of the EU. Rising global economic challenges can be mastered only with a strong, united Europe, according to the VDMA - Construction Equipment and Building Material Machinery Association. VDMA represents more than 3,200 mostly medium-sized companies in Germany’s mechanical and plant engineering sector. This was the view by attendees at the VDMA’s constructi
  • ARTBA predicts US construction infrastructure growth
    December 3, 2012
    The American Road and Transportation Builders Association’s (ARTBA) annual forecast suggests that the US transportation construction infrastructure market will show modest growth in 2013. According to ARTBA’s forecast, this segment will increase 3% to US$130.5 billion in 2013. The association’s chief economist, Dr Alison Premo Black, said that growth is expected in highway and street pavements, private work for driveways and parking lots and also airport terminal and runway work. But ARTBA predicts the brid